Concrete Placement, Finishing & Curing

Foundations

Placement Methods

MethodRateBest For
Boom pump60–150 m³/hrFoundations, slabs, reach 32–63 m
Line pump15–60 m³/hrInterior, long runs, small pours
Crane & bucketVariableStiff mixes, high-rise, no pump access
Direct chuteTruck speedClose access, chute reach 3.5–6 m

Cold Joints (CSA A23.1 Cl. 7.4.2)

Each layer must be placed before preceding layer takes initial set (60–90 min typ.). Pre-calculate pour rate and truck count.

Max Free-Fall

1.5 m max drop to avoid segregation. Use tremie or elephant trunk for deep pours.

Vibration & Consolidation

Head Dia.RadiusSpacing (1.5×r)Use
25 mm75–150110–225 mmThin, tight rebar
38 mm130–250200–375 mmGeneral work
50 mm200–350300–525 mmFootings, thick
75 mm300–500450–750 mmMass concrete

Technique

Power Trowelling Sequence

PassToolPitch
1 — FloatFloat panFlat (0°)
2 — 1st trowelTrowel bladesLow (5–10°)
3 — 2nd trowelTrowel bladesMedium (15–25°)
4 — Final burnTrowel bladesHigh (30–40°)

NEVER trowel bleed water into surface. Wait for sheen to disappear and ~5 mm footprint.

Screeding Tolerance

±6 mm over 3 m straightedge for hard-trowel slabs. Laser screed: ±3 mm.

Curing (CSA A23.1 Table 19)

ExposureMin. CureStrength
C-1, C-2 (structural)3 days70% f'c
F-1 (freeze-thaw mod.)3 days70% f'c
F-2 (freeze-thaw severe)7 days70% f'c
C-XL (extended life)7 days70% f'c

Curing Methods

Sawcut Control Joints

Parameter150 mm Slab
Depth (early-entry)≥1/4 slab = 38 mm
Depth (conventional)≥1/3 slab = 50 mm
Max spacing3.6–5.4 m (24–36 × thickness)
Ideal timing (20°C)6–18 hrs; early-entry 4–6 hrs
Panel aspect ratio≤1.5:1

When in doubt, cut sooner. Plan joints at all re-entrant corners and column block-outs.

Temperature Protocols

Hot Weather (>27°C)

Cold Weather (<5°C)

Safety — Do Not Forget

Pro Tips