| Method | Best Soils | Max Drawdown | Cost |
|---|---|---|---|
| Sump pumping | Clay, silt | Exc. depth | $ |
| Wellpoints (single) | Sand, gravel | 4.5–6 m | $$ |
| Wellpoints (2-stage) | Sand, gravel | 10–12 m | $$$ |
| Deep wells | All types | 20+ m | $$$ |
| Eductors | Silt, fine sand | 25–30 m | $$$$ |
| Soil | Spacing |
|---|---|
| Coarse sand/gravel | 0.5–1.0 m |
| Medium sand | 1.0–1.5 m |
| Fine sand | 1.5–2.0 m |
| Silty sand (marginal) | 1.0–1.5 m |
| System | Max Depth | Water Cutoff | Vibration |
|---|---|---|---|
| Soldier pile & lagging | 15+ m | Poor | Low–mod |
| Sheet piling | 12–18 m | Good–exc. | Mod–high |
| Secant pile wall | 25+ m | Excellent | Very low |
| Tangent pile wall | 20+ m | Poor–fair | Very low |
| Soil nail wall | 12–15 m | None | Very low |
| Braced (struts) | 20+ m | Varies | Low |
| Structure | Limit |
|---|---|
| Heritage / historic | 5–12 |
| Residential (good cond.) | 12–25 |
| Commercial / industrial | 25–50 |
| Reinforced concrete | 50 |
| Buried utilities (concrete) | 50 |
| Buried utilities (plastic) | 100 |
Pre-construction survey required within 30 m of pile driving. Seismograph must be calibrated within 12 months.
| Volume | Permit Required | Processing |
|---|---|---|
| ≤50,000 L/day | None | — |
| 50K–400K L/day | EASR (low-risk) | Immediate |
| >400K L/day or high-risk | Full PTTW | 90–120 days |
Fines: $100K/day individual, $1M/day corporation (OWRA). Up to $1M + 3 yrs (Fisheries Act).