Dewatering, Shoring & Excavation Support

Site Work

Dewatering Method Selection

MethodBest SoilsMax DrawdownCost
Sump pumpingClay, siltExc. depth$
Wellpoints (single)Sand, gravel4.5–6 m$$
Wellpoints (2-stage)Sand, gravel10–12 m$$$
Deep wellsAll types20+ m$$$
EductorsSilt, fine sand25–30 m$$$$

Wellpoint Spacing

SoilSpacing
Coarse sand/gravel0.5–1.0 m
Medium sand1.0–1.5 m
Fine sand1.5–2.0 m
Silty sand (marginal)1.0–1.5 m

Shoring System Selection

SystemMax DepthWater CutoffVibration
Soldier pile & lagging15+ mPoorLow–mod
Sheet piling12–18 mGood–exc.Mod–high
Secant pile wall25+ mExcellentVery low
Tangent pile wall20+ mPoor–fairVery low
Soil nail wall12–15 mNoneVery low
Braced (struts)20+ mVariesLow

Soldier Pile Specs

Vibration Limits (PPV mm/s)

StructureLimit
Heritage / historic5–12
Residential (good cond.)12–25
Commercial / industrial25–50
Reinforced concrete50
Buried utilities (concrete)50
Buried utilities (plastic)100

Pre-construction survey required within 30 m of pile driving. Seismograph must be calibrated within 12 months.

Regulatory Thresholds

Water Taking (OWRA)

VolumePermit RequiredProcessing
≤50,000 L/dayNone
50K–400K L/dayEASR (low-risk)Immediate
>400K L/day or high-riskFull PTTW90–120 days

Tieback Testing

Monitoring Triggers

Code & Permit References

Fines: $100K/day individual, $1M/day corporation (OWRA). Up to $1M + 3 yrs (Fisheries Act).

Discharge & Sediment Control

Safety — Do Not Forget

Pro Tips