Concrete & Soil Testing

TestStandardFrequency / Target
Concrete cylindersCSA A23.2-9C1 set / 75 m³ or 1/day min.
AcceptanceCSA A23.1Avg. 3 ≥ f′c; none < f′c − 3.5 MPa
Concrete maturityCSA A23.2-19CWinter pours / early strip
Soil (nuclear)ASTM D69381/250 m² per lift; 95% Proctor
Soil (non-nuclear)ASTM D7698/D7830Geotech approval required
Masonry prismsCSA A369.11 set per mix/grout combo

All testing by CCIL-accredited labs. Nuclear gauge: CNSC licence required.

Structural Steel & Welding

InspectionStandardRequirement
Bolt torque (A325/A490)CSA S16100% of slip-critical connections
Visual weld inspectionCSA W59 / CWB100% of structural welds
UT (ultrasonic)CSA W59All CJP welds in primary members
MT (magnetic particle)CSA W59Fillet welds per engineer spec

Building Envelope Testing

TestStandardTarget
Blower door (whole bldg)NECB / SB-10≤0.25 L/(s·m²) at 75 Pa
Air barrier adhesionASTM D4541200–600 kPa; 1/500 m²
Roof — flood testMfr. / ASTM50–75 mm water, 24–48 hr
Roof — ELDASTM D7877Pinpoint defects to mm
Window/door field testAAMA 502 / CSA A44010% of units or 1/type min.

MEP System Testing

SystemTest Pressure / TargetDuration
Plumbing (water)Op. + 350 kPa or 700 kPa2 hr, no drop
Plumbing (DWV)Per OPC §7.4Per code
Sprinkler (NFPA 13)1 400 kPa (200 psi)2 hr, no drop
Duct leakage (SMACNA B)3% max at rated pressure
Duct leakage (SMACNA A)1% max at rated pressure
Megger insulation500–1 000 V DC≥1 MΩ

Church-Specific Acoustic Targets

Fire Alarm & Commissioning

Required Certifications

DisciplineCertification
Concrete / masonry labCCIL-accredited
Nuclear density gaugeCNSC licence
Welding inspectionCWB-certified inspector
NDT (UT, MT, RT)CGSB/CSNDT Level II
Air barrier QAABAA-accredited
Fire alarm verificationULC-listed company
Electrical testingLicensed electrician / NETA
Plumbing pressure306A licensed plumber
Sprinkler hydrostatic427A sprinkler fitter
Commissioning agentASHRAE / BCxA certified

Critical Rules — Never Skip a Hold Point

Pro Tips