Winter Construction

General

Cold Weather Concrete (CSA A23.1 Cl. 13)

ParameterRequirement
Cold weather definedAir <5°C or expected <5°C within 24 hrs
Concrete temp at placementMin 10°C thin (<300 mm); 5°C mass
Protection periodMaintain >10°C until 7 MPa reached
Gradual cooling rateMax 1°C/hour (thin sections)
Monitoring frequencyEvery 4 hrs (first 72 hrs), then 8 hrs
Hot water from plant60–80°C (never >80°C)
Type HE cement7 MPa in 24–36 hrs vs. 48–72 hrs (GU)
Air entrainment C-2 / C-15–8% / 4–7%
Max w/c ratio0.40–0.45 (cold weather)

Reject ANY load below 10°C (thin) or 5°C (mass). No exceptions.

Cold Weather Masonry (CSA A371)

ParameterRequirement
Mortar temp at placementMin 15°C
Masonry unit tempAbove 0°C; no saturated frozen units
Protection period24 hrs min — mortar must not freeze
Wind protectionRequired >25 km/h & <5°C
Mortar board max time30 min; discard if <10°C
Mix water temp50–70°C (add to sand first)
Antifreeze admixturesNOT endorsed for structural masonry
Grout in CMU cellsPre-heat wall 12 hrs before grouting

Frozen mortar = zero bond strength. Wall collapse at first thaw.

Temporary Heating

Heater TypeOutputKey Rule
Indirect-fired100–1,000 MBHDefault — no CO inside
Direct-fired75–400 MBHLarge ventilated only + CO monitor
Hydronic (glycol)200–1,500 MBHUnder-slab, perimeter, thawing
Electric forced air15–150 kWZero CO; small enclosures

CO Monitoring Protocol

LevelAction
25 ppm (OEL TWA)Increase ventilation; fix source; evacuate if not <25 in 15 min
50 ppmEvacuate immediately; re-enter only <10 ppm
200 ppmDisorientation in 2 hrs
800 ppmUnconsciousness in minutes

Cold Stress Thresholds

TemperatureProtocol
Below −10°C10-min warm-up break every hour
Below −20°C15-min warm-up every 45 min
Below −25°C wind chillSuspend outdoor work (unless heated enclosure)

Winter Heights & Visibility

Regulatory References

Safety — Do Not Forget

Pro Tips