Quick Reference — Precast Floor Slabs at a Glance

Common Slab Sizes

DepthWeightTypical Span
150 mm (6″)~220 kg/m²Up to 6 m
200 mm (8″)~280 kg/m²Up to 9 m
250 mm (10″)~340 kg/m²Up to 11 m
305 mm (12″)~400 kg/m²Up to 14 m
355 mm (14″)~460 kg/m²Up to 16 m

Minimum Bearing Lengths

Support TypeMin.Recommended
CMU / grouted masonry65 mm75–90 mm
Cast-in-place concrete beam75 mm90–100 mm
Steel beam (bearing plate)50 mm75 mm
Precast beam / inverted tee75 mm90 mm

Key Specs

ItemValue
Standard slab width1220 mm (4′)
Keyway grout gap15–25 mm
Grout strength (min.)30 MPa non-shrink
Self-levelling topping~25 mm typical
Grout temp. range10°C–30°C
Bearing padNeoprene 6 mm, 75–100 mm wide
Bearing surface tolerance± 6 mm across wall

Safety Essentials

  • Fall protection mandatory above 2.4 m (Ont. Reg. 213/91). Guardrails on all open edges and openings.
  • One signaller only for crane operations — CSA Z150 hand signals.
  • Never cut prestressing strands without written engineer approval.
  • Grout is caustic (pH 12–13) — wear rubber gloves, long sleeves, eye protection.
📄 Download printable cheat sheet

Precast hollow-core slabs are one of the most efficient floor systems in commercial construction — and they’re a regular part of our church projects. A single truckload of slabs can cover 100–150 m² of floor area, and a good crane crew can set an entire floor in a day or two. But “fast” doesn’t mean “simple.” Every slab weighs 2–8 tonnes, the bearing details are unforgiving, the grouting has to be right, and the topping — if there is one — ties the whole system together structurally. Get any of those wrong and you’ve got a floor that bounces, cracks, or worse.

This guide covers the full sequence: delivery and site planning, crane erection, bearing and connection details, keyway grouting, composite topping placement, and the inspections that keep everyone honest. Every crew member involved needs to understand it from the ground up — literally.

Precast is the fastest floor you’ll ever build and the least forgiving if you rush the details. The slabs go up in hours. The grout and topping take days. The temptation is to skip ahead. Don’t.

— The superintendent who has seen what happens when you skip the grout

Regulatory: Precast concrete floor systems must comply with CSA A23.3 (Design of Concrete Structures), CSA A23.4 (Precast Concrete — Materials and Construction), and the Ontario Building Code Part 4. Erection and connection details are specified by the precast engineer of record. All structural connections require inspection by the engineer or their designated inspector before being concealed. Never modify bearing conditions, cut cores, or add openings without written approval from the engineer.

1. Understanding Hollow-Core Slabs

Hollow-core slabs are precast, prestressed concrete planks with continuous voids (cores) running their length. The cores reduce weight without sacrificing structural depth, and the prestressing strands give the slab its load-carrying capacity. They arrive on site ready to set — no formwork, no shoring, no curing time before you can walk on them.

Common Slab Sizes

DepthWidth (typ.)WeightTypical SpanCommon Use
150 mm (6″)1220 mm (4′)~220 kg/m²Up to 6 mShort-span mezzanines, corridors
200 mm (8″)1220 mm (4′)~280 kg/m²Up to 9 mClassrooms, offices, fellowship halls
250 mm (10″)1220 mm (4′)~340 kg/m²Up to 11 mSanctuaries, large open spans
305 mm (12″)1220 mm (4′)~400 kg/m²Up to 14 mLong-span sanctuaries, gymnasiums
355 mm (14″)1220 mm (4′)~460 kg/m²Up to 16 mHeavy loads or very long spans

The precast engineer selects the slab depth based on span, loading (dead load + live load), and fire rating requirements. For most of our two-storey church projects, 200 mm or 250 mm slabs cover the typical 7–10 m spans in sanctuary and fellowship hall areas. Deeper slabs (305–355 mm) come into play for large open sanctuaries where columns aren’t an option.

Key Terminology

Hollow cores Hollow-Core Slab Cross-Section Prestressing strands Keyway 200 mm 1220 mm (4′) typical width Composite topping (if specified)
Figure 1 — Typical 200 mm hollow-core slab cross-section showing cores, prestressing strands at bottom, keyway profiles on edges, and optional composite topping.

2. Pre-Erection Planning

A precast floor installation is a crane day — and crane days are expensive. Every minute the crane sits idle because something isn’t ready costs money and pushes the schedule. The planning you do in the week before erection determines whether it’s a smooth one-day set or a two-day disaster.

Site Readiness Checklist

  1. Bearing surfaces ready: Walls, beams, or ledgers must be at the correct elevation and have reached adequate strength. For masonry bearing walls, the grout in the bond beam course must have cured at least 48 hours. For cast-in-place concrete beams, the engineer specifies minimum strength (typically 75% of f′c) before loading with precast.
  2. Bearing surfaces level: Check every bearing point with a laser level or total station. The tolerance is tight — ± 6 mm across any bearing wall. If the wall is out of level, the slabs will rock, and shimming 4-tonne planks is nobody’s idea of fun.
  3. Bearing pads placed: Neoprene or fibre bearing pads (typically 75–100 mm wide × slab width × 6 mm thick) must be set at every bearing location before the crane arrives. The pads distribute the slab reaction and prevent point loading on the wall. Set them to the back edge of the bearing area — the slab face should be flush with or slightly recessed from the wall face.
  4. Crane setup area clear: Confirm the crane pad location, ground conditions (can it handle the outrigger loads?), swing radius, and any overhead hazards (power lines, trees). The crane operator needs a rigging plan showing slab weights, pick radii, and sequence.
  5. Delivery route confirmed: Flatbed trucks are 15–18 m long and heavy. Verify the route from the road to the crane can handle the axle loads and turning radii. Mud season in Ontario has ruined more than one precast delivery day.
  6. Openings and blockouts: Verify all slab openings (stairwells, mechanical shafts, elevator pits) against the structural drawings. The precast supplier cuts most openings at the plant, but field openings are sometimes required — and they need to be marked before erection so the crane crew knows which slab goes where.

Pro Tip: Walk the bearing walls the day before the crane arrives and mark every slab location with spray paint — slab mark number, direction of span, and which end bears where. When the crane is running and the signaller is calling for slabs, the crew on the wall needs to know instantly where each piece goes. Confusion at this stage costs $200+/hour in crane time.

Erection Sequence Planning

The erection drawing from the precast supplier shows the slab layout, piece marks, and a suggested erection sequence. The sequence matters because:

Safety — Ontario Reg. 213/91: Fall protection is mandatory when working at heights above 2.4 m. During precast erection, this means guardrails on all open edges and around all openings, or personal fall arrest systems (harness + lifeline) anchored to an engineered anchor point. The anchor point must be rated for the number of workers attached. A rebar stub sticking out of a wall is not an anchor point.

3. Crane Erection — Setting the Slabs

This is the main event — the day the floor goes up. A well-planned erection with a good crane crew can set 30–50 slabs in a single day, covering 600–1000 m² of floor. The superintendent’s job is to keep the operation moving safely and ensure every slab lands in the right place at the right elevation.

Rigging

Hollow-core slabs are lifted with a spreader beam and slab clamps (also called “tongs” or “lifting clamps”). The clamps grip the bottom edges of the slab at two points, and the spreader beam keeps the sling angle wide enough to prevent the slab from being squeezed. Key points:

Setting Procedure

  1. Signal the crane: The designated signaller (one person, qualified, visible to the operator) directs the pick. Standard hand signals per CSA Z150. Radio communication as backup, not primary.
  2. Lift and swing: The crane lifts the slab clear of the truck, swings to the building, and brings it over the bearing walls. The slab is oriented with the span direction matching the erection drawing.
  3. Guide into position: Using tag lines, the crew guides the slab to within 150 mm of its final position. The slab is lowered slowly until it’s 50–100 mm above the bearing surface.
  4. Set on bearing pads: The crew uses pry bars or alignment bars to nudge the slab into exact position as the crane lowers the last 50 mm. The slab should land centred on the bearing pads.
  5. Check bearing length: Immediately verify the slab bearing length on both ends. Minimum bearing is specified by the engineer — typically 65 mm on masonry and 75 mm on concrete. If the bearing is short, do not release the crane — lift and reset.
  6. Check alignment: The slab edge should be tight to the adjacent slab (or the reference line for the first slab). Gaps between slabs should be consistent — typically 15–25 mm for grout keyways.
  7. Release the clamps: Only after bearing and alignment are confirmed. The signaller gives the “all clear” and the crane moves to the next piece.
Bearing Wall (CMU or concrete) Bond beam / bearing course Min. 65 mm Bearing Slab A Slab B Bearing pad Grout keyway Wall width (typ. 200–300 mm)
Figure 2 — Bearing detail showing hollow-core slabs resting on bearing pads on a CMU bond beam. Minimum bearing length (typ. 65 mm on masonry) and grout keyway between adjacent slabs.

The crane operator can only see what the signaller tells him. One signaller, one set of signals. I’ve seen jobs where three guys are all waving at the crane and the operator doesn’t know who to listen to. That’s how someone gets hurt. One signaller. Period.

— The crane coordinator who only listens to one signaller, period

Best Practice: The superintendent should be on the wall during erection with the erection drawing, a tape measure, and a marker. After each slab is set, check the bearing length on both ends and initial the slab with the piece mark. If a slab is set short, it’s infinitely easier to pick it up and reset while the crane is right there than to discover the problem after the crane has gone home.

4. Bearing & Connection Details

The connection between the precast slab and the supporting structure is where the engineering lives. Every detail matters: bearing length, bearing pad type, end anchorage, and how the slab connects to the wall or beam for diaphragm action.

Minimum Bearing Requirements

Support TypeMin. Bearing (CSA A23.3)RecommendedNotes
CMU or grouted masonry wall65 mm75–90 mmBond beam must be grouted solid at bearing
Cast-in-place concrete beam75 mm90–100 mmLedge or full-width bearing
Steel beam (with bearing plate)50 mm75 mmSteel angle or plate welded to beam flange
Precast concrete beam / inverted tee75 mm90 mmBearing pad on precast ledge

Bearing Pad Selection

End Anchorage & Diaphragm Connections

For the floor to act as a structural diaphragm (transferring wind and seismic loads to the shear walls), the slabs need to be connected to the walls and to each other. There are several common connection methods:

Best Practice: Before grouting any keyways or pouring any topping, the structural engineer (or their designated inspector) must inspect all bearing conditions, verify bearing lengths, and approve the connections. This inspection must be documented with photos and a signed inspection report. Once the grout goes in, you can’t see the bearing anymore.

5. Keyway Grouting

The grouted keyways between slabs are what turn a floor made of individual planks into a unified structural diaphragm. Without grout in the keyways, the slabs can rock independently, differential deflection creates cracks in the topping and finishes, and the floor can’t transfer lateral loads. Grouting is not optional and it’s not cosmetic — it’s structural.

Grout Mix

Grouting Procedure

  1. Clean the keyways: Blow out all debris, sawdust, ice, and standing water from every keyway with compressed air. Wet debris prevents bond. If it rained since the slabs were set, let the keyways dry or blow them out thoroughly.
  2. Pre-wet the keyway surfaces: Dampen (not soak) the concrete faces of the keyway with clean water. Dry concrete sucks the moisture out of the grout before it can hydrate, causing a weak bond. Saturated-surface-dry (SSD) is the target.
  3. Place reinforcement: If the structural drawings call for rebar in the keyways (common for diaphragm connections), place it now. Typically 10M or 15M bars, lapped at splices as specified.
  4. Mix grout: Follow the manufacturer’s water ratio exactly. Over-watering is the number one cause of grout failure. Use a measured bucket for water, not a hose. Mix in a mortar mixer or with a paddle mixer in a bucket for small quantities.
  5. Pour and rod: Pour grout into the keyway from one end, working toward the other. Use a flat steel rod or piece of rebar to push the grout into the bottom of the keyway and eliminate air pockets. Don’t just dump it in from above and hope — rod every metre of keyway.
  6. Strike off: Screed the top of the grout flush with the slab surface (if no topping) or leave it 10 mm below the surface (if a topping is coming). A flat trowel works for striking keyways.
  7. Cure: Keep the grout moist for a minimum of 24 hours. Wet burlap or a curing compound applied after initial set. Don’t let it dry out in the sun — uncured grout is weak grout.

Pro Tip: Plug the ends of the keyways at the building perimeter before grouting. A simple dam of foam backer rod or a wad of duct tape prevents the grout from running out the end and down the side of the building. If you skip this step, you’ll be chipping grout off the face of the masonry wall for the rest of the afternoon.

Safety: Cementitious grout is as caustic as concrete — pH 12–13. Wear rubber gloves, long sleeves, and eye protection when mixing and placing grout. Knee pads are a good idea too, since most of this work is done kneeling on the slab. Wash any skin contact immediately with clean water.

10M or 15M rebar (if specified) Slab Slab Non-shrink grout 15–25 mm gap
Figure 3 — Keyway grouting detail showing the interlocking profile between adjacent slabs, non-shrink grout fill, and optional reinforcement for diaphragm action.

6. Core Fills & Blockouts

Sometimes you need to fill certain cores with grout or concrete — for anchorage, load distribution, or to create solid sections around openings. This is specified by the precast engineer and shown on the erection drawings.

When Cores Get Filled

Core Fill Procedure

  1. Break open the core top: Use a hammer drill or chipping hammer to open the top of the core at the location specified. The hole should be large enough to pour grout and rod it — typically 75–100 mm diameter.
  2. Plug the core: Push a foam plug or wadded paper down the core to create a dam at the correct fill depth. Verify the plug is at the right depth by measuring with a stick.
  3. Pour non-shrink grout: Same grout as the keyways — non-shrink, 30 MPa minimum. Pour in lifts of 300 mm and rod each lift.
  4. Set anchors: If an anchor bolt is required, set it into the wet grout at the correct projection and orientation. Template it to the bolt pattern if it’s for equipment mounting.

Field-Cut Openings

Sometimes an opening isn’t shown on the original precast drawings and needs to be cut in the field — for a plumbing chase, duct penetration, or a missed mechanical sleeve. This is structural surgery and requires engineer approval.

Regulatory: Cutting or coring precast hollow-core slabs in the field requires written approval from the precast engineer. Submit an RFI (Request for Information) showing the proposed opening size, location, and which cores will be affected. The engineer will confirm whether the slab can accept the opening and what reinforcement is needed. Cutting first and asking later is how structural failures happen.

7. Self-Levelling Topping

Most church projects use a thin self-levelling layer over the precast slabs rather than a full structural composite topping. The self-levelling compound — typically about 25 mm (1″) thick — solves the practical problem of creating a flat, smooth surface for finished flooring. It compensates for the natural camber in the prestressed slabs and any differential camber between adjacent planks, without the weight, cost, and complexity of a full concrete topping with reinforcement.

When a Self-Levelling Topping Is Used

A full structural composite topping (50–75 mm with welded wire mesh) is sometimes specified by the engineer for added load capacity, diaphragm reinforcement, or fire rating upgrades — but for the majority of church projects, the 25 mm self-levelling layer is all that’s needed.

Self-Levelling Placement Procedure

  1. Verify keyway grout has cured: The keyway grout must have reached design strength (typically 48–72 hours) before placing the topping. Loading uncured keyways with wet self-leveller can crack the grout bond.
  2. Clean the slab surface: Power-sweep and blow out all debris. The slab surface must be clean and free of any material that would prevent bond — mud, sawdust, drywall dust, coffee cups, and the miscellaneous debris that accumulates on every construction floor.
  3. Prime the slab surface: Apply the manufacturer’s recommended primer to the precast surface. The primer improves bond and controls the absorption rate of the concrete substrate. Allow the primer to dry per the product data sheet — typically 1–3 hours. Some products require a second coat; follow the manufacturer’s instructions exactly.
  4. Dam perimeter and openings: Install foam backer rod or dam strips at all perimeter edges, stairwell openings, elevator shafts, and floor drains. Self-levelling compound is very fluid and will run through any gap it can find. Seal everything before you start pumping.
  5. Set gauge pins or tripods: Set depth gauges (pins or tripod markers) across the slab at 1200–1500 mm centres to control the topping thickness. Set them with a rotary laser to achieve the target elevation. The thickness will vary slightly to accommodate slab camber — thinnest at mid-span, thickest near the bearings.
  6. Pump and spread: Mix the self-levelling compound in a continuous mixer or mixing pump per the manufacturer’s water ratio. Pump onto the slab in a continuous pour, working from the far end of the room toward the exit. Use a gauge rake to spread to the correct thickness, then pass a spike roller (porcupine roller) to release trapped air.
  7. Allow to cure: Most self-levelling products are walkable in 4–6 hours and ready for floor coverings in 24–48 hours, depending on thickness and conditions. Keep traffic off the surface until it has hardened. Protect from drafts and direct sunlight during initial cure to prevent cracking.
Precast Hollow-Core Slab Self-levelling Self-levelling compound (~25 mm) ~25 mm Total depth Primer coat — slab must be clean & dry Prestressing strands
Figure 4 — Self-levelling topping over hollow-core slab. The thin (~25 mm) self-levelling layer creates a flat, smooth surface for finished flooring. A primer coat at the interface ensures proper bond to the precast surface.

Self-leveller looks easy — just pump it and let it flow, right? Wrong. Skip the primer, leave dust on the slab, or let a draft hit it while it’s curing, and you’ll be back in two weeks with a scraper peeling up sheets of expensive gypsum dust. Prep is everything.

— The concrete foreman who can hear a delaminated topping from across the building

Pro Tip: Self-levelling compound is unforgiving about temperature. Below 10°C it won’t flow properly or develop strength; above 30°C it sets too fast and you get lap marks. Check the product data sheet for temperature limits and plan your pour accordingly. If you’re doing it in winter, the building needs to be enclosed and heated the day before, the day of, and at least 24 hours after the pour.

8. Handling Special Conditions

Camber & Differential Camber

Every prestressed slab has camber — an upward bow caused by the eccentric prestressing force. This is normal and expected. The camber decreases over time as the concrete creeps under sustained load. The challenge on site is differential camber: adjacent slabs with different camber values, creating a step or lip at the joint.

Cold Weather Grouting

Ontario winters and precast grouting don’t mix well. Grout that freezes before reaching initial set has zero strength — it turns to sand. If you must grout in cold weather:

Services Through Slabs

Running mechanical and electrical services through hollow-core slabs requires coordination with the precast engineer:

Best Practice: All penetration locations should be coordinated and marked on the precast erection drawings before the slabs are produced. Factory-formed openings are clean, precise, and structurally accounted for. Field-drilled penetrations are a compromise at best. The more planning you do before erection, the less drilling you do after.

9. Inspections & Quality Control

Precast floor installations involve structural connections that get permanently concealed by grout, topping, and finishes. Once covered, nobody can see whether the bearing was adequate, the keyways were grouted, or the connections were made. That’s why the inspection protocol for precast work is rigorous — and why documentation matters more here than almost anywhere else on the project.

Inspection Stages

StageWho InspectsWhat to Verify
Pre-erectionSuperintendentBearing surfaces level and at correct elevation; bearing pads in place; crane setup approved; erection drawing on site
During erectionSuperintendent + precast erectorEach slab: bearing length (both ends), alignment, piece mark vs. drawing, gap width for keyways
Post-erection / pre-groutStructural engineer or inspectorAll bearing lengths; connection details (embeds, anchorage); slab condition (cracks, damage); openings match drawings
Post-grout / pre-toppingSuperintendentAll keyways fully grouted (no voids visible); grout cured minimum time; core fills complete; slab surface clean for topping
Pre-pour (topping)Superintendent + engineer (if required)Mesh/rebar placement and cover; screed elevations; surface preparation (clean, SSD); control joint layout

Documentation

Regulatory: Under the Ontario Building Code, the structural engineer of record is responsible for confirming that the precast installation conforms to the design. This requires field inspection. A verbal “looks good” over the phone is not an inspection. The engineer must visit the site, observe the bearing conditions, and provide written confirmation before concealment. If this step is skipped and a problem surfaces later, the liability chain goes straight back to the general contractor. Don’t skip it.

10. Common Problems & How to Avoid Them

ProblemCausePrevention
Slab doesn’t fit — too long or too shortMeasurement error in supporting structure, or slab fabricated to wrong lengthVerify all span dimensions with total station before ordering slabs. Confirm with precast supplier at shop drawing stage.
Inadequate bearing lengthWall built in wrong location; slab shifts during settingSurvey wall locations before erection. Check bearing immediately after each slab is set, while crane is still rigged.
Grout voids in keywaysDebris in keyway; grout too stiff; insufficient roddingClean keyways with compressed air. Mix grout to proper flowability. Rod every metre of keyway.
Topping delaminationDirty or dry slab surface; topping placed on frozen surfacePower-sweep and pre-wet slab to SSD condition. Never pour topping on frozen or frost-covered slabs.
Excessive differential camberAdjacent slabs produced at different ages or with different strand patternsRequest camber matching from supplier. Use topping to level. Accept that some variation is inherent in prestressed products.
Cracked slab during handlingImproper rigging (single-point pick, lifting from ends without spreader beam)Always use spreader beam with proper clamps. Follow supplier’s rigging instructions. Never drag or slide slabs.
Prestressing strand cut during field coringCore drill hit strand; no X-ray or GPR scan done beforehandScan with GPR before any field penetration. Submit RFI to engineer. Use the precast shop drawings to locate strands.

Every problem on this list has happened on a real project. Most of them happened because someone was in a hurry. Precast rewards patience and punishes shortcuts. Take the extra 15 minutes to measure, check, and document. Your future self will thank you.

— The project manager who has the troubleshooting table memorized

Quick-Reference: Precast Floor Installation Checklist

  1. Pre-erection: Bearing walls/beams at elevation? Bearing pads placed? Crane plan approved? Erection drawing distributed?
  2. Delivery: Truck access confirmed? Slab piece marks match delivery ticket and erection drawing? Any visible damage?
  3. Erection: Each slab — bearing length checked (both ends)? Alignment to adjacent slabs? Keyway gaps consistent? Piece mark logged?
  4. Post-erection inspection: Engineer notified? All connections verified? Written sign-off received before grouting?
  5. Grouting: Keyways clean and pre-wet? Non-shrink grout mixed to spec? All keyways filled, rodded, and struck off? Core fills complete? Perimeter dammed?
  6. Topping (if applicable): Grout cured? Slab surface clean and SSD? Mesh on chairs? Screed rails set to elevation? Concrete ordered for correct volume?
  7. Post-pour: Topping cured for 7 days minimum? Control joints cut within 24 hours? Flatness checked?
  8. Documentation: Erection log, bearing photos, engineer’s report, grout records — all filed in QA package?

Trade Certification & Continuing Education

Precast concrete erection in Ontario falls primarily under the Ironworker (Structural/Ornamental) trade (420A), since it involves crane rigging, signalling, and setting structural elements. However, on our projects the crew doing the grouting, topping, and finishing work are typically our Cement (Concrete) Finisher (310C) and General Carpenter (403A) apprentices and journeypeople. Understanding precast systems gives your team a significant advantage — the more your people know about how the slabs work structurally, the better they handle the details that keep the floor performing for decades.

Best Practice: Before every precast erection day, hold a pre-erection meeting with the crane operator, signaller, setting crew, and superintendent. Review the erection sequence, rigging plan, slab weights, fall protection plan, and emergency procedures. Everyone on the crew needs to understand the plan before the first slab leaves the truck. This meeting is documented and filed.

A good precast day is one of the most satisfying things in construction. You show up in the morning with bare walls and by the end of the day you’re standing on a floor. There’s nothing else in this trade that moves that fast. But fast only works when the planning was slow and careful. Do the homework, and the crane day takes care of itself.

— The superintendent who stood on 45 slabs by 4 PM and still had energy to brag about it

Recommended Videos

Back to Employee Portal