Quick Reference — Structural Steel Erection, Bolting & Connections

Erection Tolerances (CSA S16-19)

ParameterCSA S16 ToleranceHCMI Target
Column plumbH/500H/1000
Beam elevation±10 mm±5 mm
Column spacing±5 mm/bay±3 mm/bay
Cumulative plan position±25 mm max±15 mm max
Anchor bolt position±6 mm±3 mm
Base plate elevation±6 mm±3 mm

High-Strength Bolting (ASTM F3125)

Old NameF3125 GradeMin TensileRe-usable?
A325Grade A325830 MPaOnce
A325TCGrade F1852830 MPaNo
A490Grade A4901,040 MPaNever
A490TCGrade F22801,040 MPaNever

Turn-of-Nut Rotation

  • L ≤ 4d: 1/3 turn (120°)
  • 4d < L ≤ 8d: 1/2 turn (180°)
  • 8d < L ≤ 12d: 2/3 turn (240°)
  • Snug all bolts first, mark reference line, then rotate
  • Skidmore-Wilhelm calibration: 3 bolts per lot, start of each shift

Connection Types

ConnectionTransferMin Bolts
Shear tabShear only2–5 vertical
Double angleShear only2–4 per angle
End plate (flush)Shear + moment4–8
End plate (extended)Full moment8–12
Moment (flange-welded)Full momentWeb bolted, flanges CJP

Metal Deck & Shear Studs

  • Min 50 mm bearing on supports; side laps fastened ≤900 mm o.c.
  • Puddle welds: 19 mm dia, 300 mm o.c. at supports (CWB welder)
  • Shear studs: 19 mm dia, min 75 mm above deck rib
  • Bend test: first 2 studs per run, 15° bend — no crack = pass

Rigging Hitch Capacity

  • Vertical hitch: 100% of sling WLL
  • Choker hitch: 75% of sling WLL
  • Basket hitch: 200% of sling WLL
  • Deduct rigging weight (300–500 kg) from crane rated capacity

Safety Essentials

  • Min 2 erection bolts per connection before crane release (O. Reg. 213/91 s.154)
  • Written erection plan required on site (s.153) — no steel leaves ground without it
  • Fall protection at >3 m (s.26.1) — guardrail, net, or fall arrest
  • Joists: bridge as you go — no worker on unbridged joist
  • Lifts >80% crane capacity = critical lift plan required
  • Temporary bracing stays until permanent lateral system complete + engineer approved
📄 Download printable cheat sheet

Steel day is the best day on any church project. Concrete guys will argue, but concrete guys argue about everything. When that first column goes vertical and the crane swings the first beam into place, the building stops being lines on paper and starts being a building. There’s a reason ironworkers walk a little taller than everyone else on site — they’re literally building the skeleton that holds everything up.

But steel erection is also where things can go catastrophically wrong if you don’t know what you’re doing. A misaligned anchor bolt is a headache. An under-torqued high-strength bolt is a lawsuit. A column that’s out of plumb by 25 mm at the base becomes 75 mm off at the roof, and suddenly your curtain wall doesn’t fit and someone’s writing a very expensive cheque.

This guide covers the full scope of structural steel work on church projects — from the moment the first truck rolls in with columns on the flatbed to the last shear stud welded on the composite deck. Real procedures, real tolerances, real numbers. The kind of stuff that keeps engineers happy and keeps ironworkers from having to do things twice.

An ironworker’s lunch pail has three things: a sandwich, a thermos, and a drift pin. Lose any one of them and you can’t work.

— The foreman who judges a new hire by the contents of his lunch pail

Best Practice: All structural steel erection must follow a site-specific erection plan reviewed by the steel erector, the engineer of record, and the project manager. No steel leaves the ground until that plan is signed off. No exceptions — not even if the crane is already on site and the operator is charging by the hour.

1. Erection Planning & Sequence

Every HCMI steel erection starts with a plan. Not a “we’ll figure it out when the crane gets here” plan — an actual, written, reviewed erection plan per CISC guidelines. This document lives in the site trailer and everyone touching steel has read it.

What the Erection Plan Covers

O. Reg. 213/91 — Construction Projects, s. 153: No structural steel shall be erected unless a written procedure has been developed and is available at the project. The procedure must address erection sequence, temporary bracing, and connection requirements. Violation is a stop-work order.

Crane Selection Basics

You don’t pick a crane based on the heaviest piece alone. You pick it based on the heaviest piece at the farthest radius. A W18×50 beam weighing 2,200 kg at 30 m radius needs a very different crane than the same beam at 15 m. Always work from the crane’s load chart — never from memory, never from “we used the same crane last job.”

Pro Tip: When reviewing the crane load chart, always deduct the weight of rigging from the crane’s rated capacity. A spreader bar, four chain slings, and shackles can easily add 300–500 kg. That matters when you’re working at long radius.

2. Column Setting

Columns are the first steel to go vertical, and everything that follows depends on getting them right. A column that’s 5 mm out of position at the base is a column that’s out of position forever. The engineer designed it in one spot; your job is to put it in that spot.

Base Plate Shimming & Grouting

  1. Verify anchor bolt positions against the Leica total station layout (see the Survey Layout & Control article). A good standard tolerance for anchor bolt placement is ±3 mm from design. If they’re outside that, stop and call the engineer before trying to make it work.
  2. Set levelling nuts on all anchor bolts to the correct elevation. Use the total station or a precise builder’s level to set all nuts to within ±1.5 mm of design bearing elevation.
  3. Place steel shim stacks at a minimum of three points per base plate (four for plates larger than 450 mm square). Shims must be full-bearing — no rocking. Maximum shim stack height: 75 mm; if you need more, the concrete is wrong.
  4. Fly the column and land it on the shims. Guide it onto the anchor bolts using drift pins if needed.
  5. Thread anchor bolt nuts hand-tight, then snug with a wrench. Do not fully torque yet — you’ll need adjustment room for plumbing.
  6. Grout after plumbing: Non-shrink grout (Masterflow 928 or equivalent) is placed after the column is plumbed and the anchor bolts are fully tightened. Minimum 25 mm grout bed; maximum 75 mm. Allow 24–48 hours cure before releasing temporary bracing.

The anchor bolts are never where you need them to be. They’re close. Close enough to give you hope. But never exactly right. That’s what drift pins and strong language are for.

— Every ironworker since 1952

Plumbing Columns with Guy Wires

Once the column is standing and initially bolted, it needs to be plumbed — made perfectly vertical in both axes. CSA S16 allows a plumb tolerance of H/500, where H is the column height. For a typical 6 m church column, that’s 12 mm maximum out-of-plumb. Best practice is to target H/1000 so that curtain walls actually fit.

Tolerance: H/500 (CSA S16) — Best practice: H/1000 W-Shape Column Guy Wire Guy Wire T-buckle T-buckle Dead Man Dead Man Plumb Line Base Plate / Grout Bed
Figure 1 — Column plumbing setup: guy wires with turnbuckles anchored to dead-man weights or slab anchors. Adjust turnbuckles to bring the column within tolerance, then verify with the Leica total station.

The procedure is straightforward but demands patience:

  1. Attach a minimum of two guy wires at approximately 2/3 column height, oriented 90° apart.
  2. Anchor the far ends to dead-man weights (minimum 2,000 kg) or cast-in slab anchors.
  3. Install turnbuckles in-line on each guy wire.
  4. Using the Leica total station in stake-out mode, check the column centre at the top against the design coordinates.
  5. Adjust turnbuckles to bring the column into plumb. Work one axis at a time.
  6. Re-check with the total station — both axes, both faces. Confirm H/1000 or better.
  7. Fully torque anchor bolt nuts. Re-verify plumb — torquing can pull the column slightly.

Best Practice: All column plumb readings must be documented on the Steel Erection Quality Log (form SE-004) with the Leica total station instrument serial number, date, and operator. These records become part of the permanent project file and are required for the engineer’s field review letter.

3. Beam Setting & Connections

Once columns are plumbed and secured, beams start flying. A good connector crew can set and bolt 15–20 beams per hour in an efficient sequence. A bad sequence turns that into five beams per hour with the crane sitting idle half the time. The erection plan dictates the sequence; the connectors execute it.

Connection Types on Church Projects

Connection TypeTransferTypical LocationBolt Group
Shear tab (single plate)Shear onlyGravity beams to columns2–5 bolts, vertical line
Double angleShear onlyBeam-to-beam, beam-to-girder2–4 bolts per angle
End plate (flush)Shear + limited momentContinuous beams, portal frames4–8 bolts, rectangular pattern
End plate (extended)Full momentMoment frames (sanctuary clear spans)8–12 bolts, extended above/below flanges
Moment (flange-welded)Full momentSpecial moment framesWeb bolted, flanges CJP welded

Fit-Up Procedure

  1. Signal the crane to bring the beam into position. The connector on the column guides the beam end into the connection using hand signals (see Section 12 for signals).
  2. Drive a drift pin through the first hole to align the bolt pattern. Drift pins go through at least one bolt hole per connection before the crane load is released.
  3. Install erection bolts: A minimum of two erection bolts per connection (CISC requirement). Erection bolts must be the same diameter and grade as the final bolts. Snug them tight.
  4. Signal the crane to release. Confirm the beam is stable on erection bolts before the choker is pulled.
  5. Install remaining bolts and bring all bolts to snug-tight as a minimum. If the connection requires pretensioning, that’s a separate step (Section 4).

Gravity works 24/7 and it never takes a lunch break. If you don’t have two bolts in that connection before you unhook the crane, gravity will remind you why the rules exist.

— The safety coordinator nobody wants to see walking toward their connection

O. Reg. 213/91, s. 154(1): A structural steel beam or similar member shall not be released from a hoisting device unless the member is adequately secured to prevent displacement. Minimum two bolts per connection, snug-tight, before the load is released.

4. High-Strength Bolting

This is where a lot of crews get sloppy, and it’s where inspectors spend most of their time. High-strength bolting isn’t just “tighten it until it feels good” — it’s a controlled, inspectable, documented procedure with specific torque values, rotation angles, and verification requirements.

Bolt Grades: The New Naming

The old ASTM A325 and A490 designations have been consolidated under ASTM F3125 (referenced in CSA S16). Same bolts, new name, same arguments about which one to use:

Old NameF3125 GradeMin. Tensile (MPa)Use
A325Grade A325830Most connections, re-usable (once)
A325TCGrade F1852830Tension-control (twist-off) version of A325
A490Grade A4901,040Heavy moment connections, NOT re-usable
A490TCGrade F22801,040Tension-control version of A490

Snug-Tight vs. Pretensioned

Not every bolt needs pretensioning. CSA S16 and the RCSC Specification define when each condition applies:

Best Practice: When the structural drawings specify “pretensioned” or “slip-critical,” every bolt in that connection gets pretensioned. No mixing. No “close enough.” The bolt installation procedure must be verified using a Skidmore-Wilhelm bolt tension calibrator at the start of each shift and whenever the bolt lot changes.

Turn-of-Nut Method — Step by Step

The turn-of-nut method is the most reliable and most commonly used pretensioning method on church projects. Here’s the procedure, exactly as RCSC and CSA S16 require it:

1

Snug all bolts in the group. Use an impact wrench to bring every bolt in the connection to snug-tight. Work from the stiffest part of the connection outward (typically centre of the bolt group toward the edges).

2

Mark the reference line. Using a paint marker or lumber crayon, draw a straight line across the nut, washer, and connected steel. This is your “snug line” — it marks the starting point for rotation measurement.

3

Apply the specified rotation from the snug-tight condition. The required rotation depends on bolt length relative to diameter:

  • Bolt length ≤ 4× diameter: 1/3 turn (120°)
  • Bolt length > 4d but ≤ 8d: 1/2 turn (180°)
  • Bolt length > 8d but ≤ 12d: 2/3 turn (240°)
4

Inspect the marks. The paint line on the nut should have rotated the specified amount relative to the line on the steel. If it’s under-rotated, apply more. If it’s over-rotated by more than about 30°, the bolt must be replaced (A490) or re-evaluated (A325).

5

Document. Record the bolt lot number, Skidmore verification result, and visual confirmation of rotation on form SE-007.

Turn-of-Nut Method — Required Rotation 120° 1/3 Turn L ≤ 4d 180° 1/2 Turn 4d < L ≤ 8d 240° 2/3 Turn 8d < L ≤ 12d Gold line = snug mark on steel   |   Red line = final nut position after rotation
Figure 2 — Turn-of-nut rotation requirements. The snug mark (gold) stays fixed on the steel; the nut rotates the specified amount past it. Mark alignment is how inspectors verify the work.

Tension-Control (TC) Bolts

TC bolts (the “twist-off” type) have a splined end that shears off at the calibrated tension. They’re fast and largely foolproof — if the spline snapped off, the bolt is tensioned. That said:

Skidmore-Wilhelm Testing

The Skidmore is a hydraulic bolt tension calibrator. Before each shift and whenever the bolt lot changes, install 3 representative bolts from the lot into the Skidmore and tighten using the same method (turn-of-nut, TC gun, or calibrated wrench) that will be used in the field. The tension reading must meet or exceed the minimum pretension per CSA S16 Table 3 (e.g., 3/4″ A325 = 125 kN; 7/8″ A325 = 173 kN).

Pro Tip: Keep a dedicated log book with the Skidmore. Each entry should have the date, bolt lot number, bolt grade, diameter, method, three tension readings, and the operator’s initials. Inspectors love a clean Skidmore log — it shows you’re serious about quality.

5. Metal Deck Installation

Once the steel frame is up and bolted, the metal deck goes down. Deck serves double duty on most HCMI church projects: it’s the form for the concrete slab and the bottom tension element of the composite floor. Get the installation wrong and you’re either pouring concrete onto the parking lot below or building a floor that deflects like a trampoline.

Deck Types & Gauges

ProfileTypical GaugeDepthUse on Church Projects
P-3615 (1.5″ composite)20 ga (0.91 mm)38 mmMezzanine floors, offices
P-3623 (3″ composite)20 or 18 ga76 mmSanctuary balconies, fellowship halls
B-Deck (1.5″ roof)22 ga (0.76 mm)38 mmRoof deck (non-composite)
N-Deck (3″ roof)20 ga76 mmLong-span roof areas

Laying Pattern

Deck sheets are laid perpendicular to the supporting beams, starting from one end of the building and working across. Key rules:

Fastening Methods

Pour Stops, Closures & Safety Netting

Pour stops are angle or channel sections at slab edges that contain the concrete during the pour. Install them before reinforcing. Deck closures are corrugated filler pieces at beams running parallel to the deck ribs — they prevent concrete from flowing into the flutes at those locations. Safety netting or equivalent fall protection must be installed below open deck areas per O. Reg. 213/91 s. 26.1 before anyone works on the deck.

Safety — O. Reg. 213/91, s. 26.1: Where a worker is exposed to a fall of more than 3 m, a guardrail system, safety net, or travel restraint/fall arrest system must be in place. Open deck areas with no concrete are fall hazards. No exceptions for “it’s only for a minute.”

6. Shear Stud Welding

Shear studs are what make a composite floor composite. Without them, the concrete slab and the steel beam act independently — two separate elements bending under load. With studs, the slab and beam act together as a T-shape, dramatically increasing stiffness and strength. A W16×31 beam with composite action can carry the same load as a W21×44 without it. That’s real money.

Nelson Stud Gun Operation

  1. Set the gun parameters: Weld time (typically 0.5–1.0 seconds), lift height (3–5 mm), and plunge depth. These are set based on the stud diameter — 19 mm (¾″) studs are standard on church projects.
  2. Load the stud into the chuck and place the ceramic ferrule.
  3. Position the gun perpendicular to the beam flange, pressing firmly.
  4. Pull the trigger. The gun lifts the stud, strikes an arc, melts the base, and plunges the stud into the weld pool. It happens in under a second.
  5. Remove the ferrule by tapping it off. Inspect the 360° weld fillet at the stud base.

Quality: Bend Test & Visual Inspection

Per CSA S16 and the CISC quality manual:

Pro Tip: If studs keep getting incomplete welds, check three things in order: (1) Is the beam flange clean? Mill scale, paint, rust, and moisture kill stud welds. Grind the flange bright before welding. (2) Is the ground clamp tight and close to the weld location? (3) Are the gun settings correct for the stud diameter and deck gauge? The Nelson manual has specific settings for through-deck vs. direct-to-flange welding.

I’ve seen guys try to weld studs through a puddle of rain water on the deck. I’ve also seen the same guys acting surprised when the studs pop off like bottle caps. Funny how that works.

— CWB welding inspector, church project in Barrie

7. Steel Joist Erection

Open-web steel joists (OWSJs) are the workhorses of church roofs. They span long distances at light weight, and they’re economical — which is important when the building committee is counting every dollar. But joists have one critical weakness: they are laterally unstable until bridging is installed. An unbridged joist is a 12-metre-long piece of steel that wants to roll over like a wet noodle.

SJI Standards & CISC Requirements

Joist Seat Connections

Joists bear on seats welded to the support beams or on bearing plates on walls. Each seat gets a minimum of two ½″ fillet welds, 50 mm long, or two ¾″ A325 bolts. The joist must not be released from the crane until the seat connection is secured and at least one row of bridging is installed to the adjacent (already-braced) joist.

Joist Girder Seats

Joist girders — the big ones that support the joists — sit on column cap plates. These connections are typically bolted with 4× ¾″ A325 bolts. The girder must be stabilised with a minimum of one joist and its bridging connected before the next girder is set.

Safety — SJI & O. Reg. 213/91: A worker shall not stand on or attach to a steel joist until the joist is fully bridged and the seat connections are complete. Multiple fatalities in Ontario have resulted from unbridged joists rolling during erection. This rule is strongly recommended.

8. Miscellaneous Metals

Not everything on a steel project is big and dramatic. A lot of the work is the smaller stuff that makes the building functional — lintels over doors, angle supports for masonry, handrails, guardrails, ladders, and embed plates. It’s less glamorous than swinging beams, but if the lintel is wrong the mason can’t lay block, and if the embed plate is wrong the precast crew is standing around billing you by the hour.

Common Miscellaneous Items

9. Steel Stairs

Steel stairs on church projects are typically pre-fabricated in the shop as flight assemblies (two stringers with treads/risers welded in) and set by crane. They’re heavier than they look — a 3.5 m floor-to-floor stair flight can weigh 800–1,200 kg.

Setting Sequence

  1. Verify landing elevations with the Leica total station. Stairs are unforgiving — the OBC requires uniform riser height within ±5 mm for the full flight. If the landings are wrong, the stairs don’t fit.
  2. Set the bottom flight first, shimming the stringer bearing points to achieve correct elevation. Use steel shims, not wood.
  3. Bolt the base connections: Typically 4× ¾″ A325 bolts at each stringer bearing.
  4. Set the intermediate landing (if applicable), then the upper flight.
  5. Grout under stringer bearing plates with non-shrink grout after final alignment is confirmed.
  6. Install temporary guardrails immediately. Stairs become circulation routes for all trades as soon as they’re in. O. Reg. 213/91 requires guards on open sides of stairs during construction.

Best Practice: Permanent guardrails on stairs must be installed within 5 working days of stair setting. In the interim, temporary guardrails (minimum 1,070 mm height with mid-rail and toe board) must be in place before any trade uses the stairs. This is tracked on the weekly safety inspection.

10. HSS Connections

Hollow Structural Sections (HSS) — round, square, and rectangular tubes — are increasingly common on church projects for exposed architectural elements, canopies, and bracing. They look great but they’re a different animal to connect than open sections like W-shapes.

Welded HSS Connections

The challenge with welding to HSS is that you can’t get inside the tube to place backing bars, and the curved or flat face of the tube means your weld angle is constantly changing. CWB W47.1 qualified welders are mandatory. Key considerations:

Bolted HSS Connections

Bolting to HSS typically requires a shop-welded tab, end plate, or through-plate because you can’t access the inside for a nut. Alternatives include blind bolts (e.g., Huck BOM, Lindapter Hollo-Bolt) that expand inside the tube. These are specialty fasteners — follow the manufacturer’s installation procedure exactly and verify torque with the calibrated wrench specified.

11. Steel Plumbing & Alignment

Getting steel plumb and aligned isn’t a one-time event — it’s a continuous process from the first column to the last roof beam. Every piece affects the next, and errors accumulate. CSA S16-19 Clause 28.6 defines the tolerance world you live in:

ParameterCSA S16 ToleranceHCMI Target
Column plumbH/500H/1000
Beam elevation±10 mm±5 mm
Column spacing±5 mm per bay±3 mm per bay
Cumulative plan position±25 mm max±15 mm max
Anchor bolt position±6 mm±3 mm
Base plate elevation±6 mm±3 mm

Verification with Total Station

The Leica total station (covered in depth in the Survey Layout & Control article) is the primary verification tool. After each erection sequence (typically each bay or each grid line), the survey crew checks:

Readings are recorded on form SE-005 and compared against the design coordinates. Any deviation beyond the project targets triggers a hold for review with the engineer before proceeding. Deviations beyond CSA S16 limits trigger a non-conformance report (NCR).

Steel is like a poker game. You can bluff your way through the first few hands, but eventually the surveyor shows up with a total station and calls every bluff you’ve got.

— The superintendent who compares steel erection to poker night

12. Rigging for Steel Erection

Every piece of steel that leaves the ground does so at the end of a rigging configuration. Bad rigging kills people. There’s no softer way to put it. This section covers the rigging fundamentals every crew member must know.

Common Hitch Types

Common Rigging Hitch Types Hook LOAD Choker Hitch Capacity: 75% of sling WLL Sling wraps & chokes around the load Hook LOAD Basket Hitch Capacity: 200% of sling WLL Both eyes return to the hook; load cradled Hook LOAD Vertical Hitch Capacity: 100% of sling WLL Direct connection via shackle or hook
Figure 3 — The three fundamental hitch types. Note the capacity reduction for choker hitches (75%) and the increase for basket hitches (200%). Always use the correct sling angle factors for non-vertical legs.

Rigging Hardware

HardwareRating BasisInspection Points
Shackles (anchor/bow)WLL stamped on bodyPin wear, body distortion, legible markings
Wire rope slingsWLL on tag; derate for hitch type and angleBroken wires (6 in one lay = reject), kinks, corrosion, crushed core
Nylon/polyester slingsWLL on label by colour codeCuts, abrasion, UV damage, heat exposure marks
Chain slings (Grade 80/100)WLL on tagStretched links (>5% = reject), gouges, cracks, twist
Spreader barsEngineered capacity on drawingWeld integrity, pin connections, straight (no bend)

Tag Lines, Hand Signals & Communication

Every steel pick uses tag lines to control the load. Minimum one tag line per end of a beam; two tag lines for columns (to prevent spinning). Tag lines must be non-conductive (polypropylene, not wire rope) when working near electrical. Never wrap a tag line around your hand or body.

A common approach is to use standard CSA hand signals for crane operations. The designated signaller wears a high-visibility vest and is the only person communicating with the crane operator during the lift (except for emergency stop, which anyone can give).

Pro Tip: Before the first pick of the day, do a “dry run” — lift the piece 150 mm off the truck, hold it, and check everything: rigging balance, tag line positions, crane capacity indicator reading, ground conditions. If something looks wrong 150 mm up, it’ll look a lot worse at 15 m.

There are only two types of riggers: the ones who check the shackle pin every time, and the ones who have a really exciting story about the time they didn’t.

— Every crane operator who has a “shackle pin story” and hopes you don’t get one

13. Temporary Bracing & Stability

Temporary bracing keeps partially-erected steel frames from becoming very expensive dominoes. Until the permanent lateral load resisting system is complete (moment frames fully bolted, braced bays complete, metal deck acting as a diaphragm), the building depends entirely on temporary bracing to resist wind, construction loads, and the not-insignificant force of a crane swinging a 3-tonne beam into the side of the frame.

Safety — CISC & CSA S16: Temporary bracing design is the responsibility of the steel erector and must be reviewed by a Professional Engineer. The erection plan must show all temporary bracing locations, connection details, and the sequence for installation and removal. Field improvisation is not acceptable.

14. Bolt Inspection & Documentation

Steel erection quality lives and dies by documentation. The best bolt installation in the world is worthless if you can’t prove it happened. Maintain a complete bolt installation and inspection record for every project.

Inspection Checklist

Best Practice: All bolt inspection records (forms SE-004 through SE-008) are maintained in the project quality binder and submitted to the engineer of record with the steel erection completion package. Missing records = incomplete work as far as the engineer is concerned.

15. Putting It All Together — Typical HCMI Church Steel Sequence

Here’s what a typical steel erection looks like on a sanctuary project, from mobilization to punch list:

  1. Day 1–2: Crane setup, rigging inspection, shakeout of first steel delivery. Survey crew verifies all anchor bolt positions. Erection plan briefing with all crew.
  2. Day 3–5: Set columns in the first bay. Plumb, brace, and bolt. Survey verification.
  3. Day 5–10: Set beams and girders, bay by bay, working from back to front. Install temporary bracing as each bay is completed. Erection bolts in, snug-tight.
  4. Day 10–12: Steel joists and joist girders for the roof. Bridging installed as each joist is set.
  5. Day 12–15: Pretensioning of all bolts requiring it. Skidmore verification. Bolt inspection and documentation.
  6. Day 15–18: Metal deck installation. Puddle welds, side laps, pour stops, closures.
  7. Day 18–20: Shear stud welding. Bend tests. Quality documentation.
  8. Day 20–22: Steel stairs, miscellaneous metals, touch-up paint.
  9. Day 22–24: Final survey verification of all steel. Engineer’s field review. Punch list.
  10. Day 25: Demobilize crane. Celebrate. Iron workers’ tradition: last beam signed by the crew.

The last beam always goes up signed. Everyone on the crew puts their name on it. Fifty years from now, when they renovate this church, some ironworker is going to find our names up there in the steel and know that we built this thing right.

— The connecting foreman who signs every last beam and means it

Key Standards & References

StandardRelevance
CSA S16-19Design and erection of steel structures — tolerances, bolting, connections
CISC Code of Standard PracticeFabrication and erection procedures for structural steel
CISC Handbook of Steel ConstructionDesign tables, connection details, bolt tension values
RCSC Specification for Structural JointsBolt installation methods, inspection, and quality
ASTM F3125 (referenced in CSA S16)High-strength bolt specifications (replaces A325/A490)
CWB W47.1 / W59Welding certification and welding code for steel structures
SJI Code of Standard PracticeSteel joist erection, bridging, and connection requirements
O. Reg. 213/91Construction Projects regulation (Ontario) — steel erection, fall protection, rigging
CSA B167Overhead crane and hoist requirements

Build it like you’re going to worship in it. Because on a church project, you just might.

— Unofficial company motto, taped to the inside of every hard hat

Recommended Videos

Back to Employee Portal