Quick Reference — Curtain Wall Framing at a Glance

Stud Specifications

ItemValue
Steel grade345 MPa (50 ksi) structural — ASTM A1003 Grade 50
Typical gauge14ga (1.73 mm) or 12ga (2.46 mm)
Typical width152 mm (6″) or 203 mm (8″)
Standard spacing400 mm (16″) o.c.
Corner/edge zonesTighter spacing or heavier gauge per P.Eng.

Deflection Limits

CladdingLimit
Brick, stone, precast (rigid)L/360
Metal panel, fibre cement (flexible)L/240
Glazing systemsL/175 (or per glazing engineer)

Clip Angle Connections

LocationTypeKey Detail
Base (fixed)L-angle, round holesRigid — resists wind shear, no vertical movement
Top (deflection)L-angle, slotted holesAllows vertical movement — bolts snugged, NOT torqued

Safety & Critical Rules

  • P.Eng. shop drawings required before any curtain wall framing begins — no prescriptive path for church projects.
  • 345 MPa steel only for structural curtain wall studs. Verify grade stamp.
  • Slotted clips: Bolts must allow vertical movement. Never fully torque.
  • Air barrier must be continuous — every joint, penetration, and transition sealed.
  • Continuous insulation outboard of studs required to control thermal bridging.
📄 Download printable cheat sheet

The exterior envelope of a church building is where structural framing meets weather, physics, and the relentless forces of Ontario winters. Curtain wall framing is the non-load-bearing exterior wall system that hangs on the primary structure — steel beams, concrete floors, or a combination of both — and its job is straightforward in concept but demanding in execution: keep the weather out, keep the heat in, resist wind loads, support whatever cladding the architect chose, and do all of this for fifty years without complaint.

On church projects, curtain wall framing shows up everywhere: the tall sanctuary facades with soaring glass, the classroom wing walls clad in brick veneer, the fellowship hall wrapped in metal panel, the office section with stone accents. Each application has the same fundamental structure — steel studs spanning between floor lines, connected to the primary structure with clip angles — but the envelope assembly, cladding system, and detailing vary dramatically.

This guide covers it all. From the clip angle at the base of the stud to the sealant joint around the last window, every layer of the building envelope is detailed here at the level a field crew needs to build it right.

The structure holds the building up. The envelope keeps the building alive. Get one layer wrong and the whole wall weeps — sometimes literally.

— The envelope consultant who’s seen more water leaks than a plumber

Best Practice: All curtain wall framing — stud sizing, clip connections, bracing, and envelope assembly — requires P.Eng. design. Curtain wall systems resist wind loads, support cladding, and form the building’s environmental separation. There is no prescriptive path for these assemblies on church projects. If the engineered drawings are not on site, the framing does not start.

1. What Is Curtain Wall Framing?

A curtain wall is a non-load-bearing exterior wall that is attached to the building’s primary structural frame. It carries no gravity loads from above — no floors, no roof, no beams bear on it. The curtain wall studs span vertically between floor lines (or between spandrel beams), and their only structural job is to resist lateral loads: wind pressure pushing inward, wind suction pulling outward, and seismic forces in some cases.

Beyond resisting wind, the curtain wall serves as the building’s environmental separation — the dividing line between inside and outside. It supports the cladding, carries the continuous insulation, provides the substrate for the air and vapour barriers, and integrates with every window, door, and penetration through the exterior wall. Every layer matters. Every joint matters. Every transition matters.

Why Churches Need Curtain Wall Framing

2. Design Principles

Curtain wall framing sits at the intersection of structural engineering and building science. The structural side sizes the studs, designs the connections, and ensures the wall resists wind without excessive deflection. The building science side designs the envelope assembly — insulation, barriers, drainage, and cladding support — to control heat, air, moisture, and vapour flow through the wall. Both disciplines must work together; a structurally adequate wall that leaks water is no better than a watertight wall that blows in during a storm.

Governing Standards

Ontario Building Code Requirements

Wind Load Design

Curtain wall studs are sized primarily for wind. The National Building Code of Canada (NBCC) provides reference wind pressures based on geographic location, and for most Ontario church projects the design hourly wind pressure (1-in-50-year return) translates to wall pressures in the range of 0.3–0.5 kPa on the main field of the wall. At building corners and roof edges, the pressures increase significantly — sometimes doubling — due to aerodynamic effects. The engineer accounts for these higher pressures by specifying heavier gauge studs or tighter spacing in corner and edge zones.

Deflection Limits

Cladding TypeDeflection LimitReason
Rigid cladding (brick, stone, precast)L/360Rigid cladding cracks or gaps if the wall flexes excessively
Flexible cladding (metal panel, vinyl, fibre cement)L/240Flexible cladding can accommodate more movement without damage
Glazing systemsL/175 to L/240Per glazing manufacturer requirements; glass is brittle

L is the unsupported span of the stud (typically floor-to-floor height). For a 3.6 m storey height with L/360, maximum allowable deflection is 10 mm under full design wind load.

All Curtain Wall Framing Requires P.Eng. Design: There is no prescriptive path for curtain wall framing on church projects (OBC Part 3, Group A buildings). Every stud size, gauge, spacing, clip detail, and bracing layout must appear on P.Eng.-sealed shop drawings. Framing from architectural drawings alone is never acceptable. If the shop drawings are not on site, the work does not proceed.

3. Stud Selection & Sizing

Curtain wall studs are heavier than interior partition studs — they must resist the full design wind pressure over their unsupported span while limiting deflection to the values required by the cladding type. The studs are cold-formed steel (CFS), manufactured from 345 MPa (50 ksi) structural-grade steel per ASTM A1003 Grade 50 or equivalent CSA standard.

Typical Stud Specifications

ParameterTypical RangeNotes
Gauge14ga (1.73 mm) or 12ga (2.46 mm)18ga used only for short spans or low wind zones; 16ga for moderate conditions
Depth152 mm (6”) or 203 mm (8”)Deeper studs resist more bending; 203 mm common for tall storey heights
Spacing400 mm (16”) o.c. standard600 mm o.c. sometimes used with heavier gauges; 300 mm for high wind zones
Flange width41 mm (1-5/8”) typicalWider flanges available for heavy cladding or specific clip connections

Corner and Edge Zones

Building corners and edges experience higher wind pressures than the main field of the wall. The engineer designates these as pressure zones, and the studs in these zones are typically upgraded — either a heavier gauge (e.g., 12ga instead of 14ga) or tighter spacing (e.g., 300 mm instead of 400 mm). The shop drawings clearly indicate where zone changes occur. Mark these transitions on the floor track during layout — a change in stud gauge is invisible once the wall is sheathed, and using the wrong stud in the wrong zone is a structural deficiency.

Stud Span

Curtain wall studs span vertically between floor lines or between spandrel beams. Typical storey heights on church projects range from 3.0 m for office and classroom areas to 6.0–10.0 m for sanctuary walls. Taller walls may require intermediate horizontal support (girts) to break the stud span into shorter segments, or deeper/heavier studs to span the full height.

Pro Tip: Always verify the stud bundle label before installation. Structural 345 MPa (50 ksi) studs and non-structural 228 MPa (33 ksi) studs look identical. They have the same dimensions and weight. But a 33 ksi stud has roughly 35% less capacity. The bundle label or mill certificate is the only reliable way to confirm the grade. No label = no installation.

4. Connection to Structure — Base (Fixed)

At the base of each storey, the curtain wall studs connect to the floor structure (concrete slab or steel beam) with clip angles that provide a rigid, fixed connection. The base clip resists wind shear forces (the horizontal component of wind load at the base of the stud) and anchors the stud against both inward pressure and outward suction. The base connection does not allow vertical movement — it is the fixed end of the stud.

Clip Angle Specifications

Installation Procedure

  1. Snap a chalk line on the floor slab or steel beam at the stud line location, verified against control dimensions.
  2. Pre-drill or pre-punch the clip angles on the ground — factory-fabricated clips with pre-punched holes are strongly preferred.
  3. Fasten the clip to the structure first (bolts or anchors), aligned to the chalk line.
  4. Set the stud into the clip and fasten with HWH screws through the pre-punched holes in the clip’s vertical leg into the stud web.
  5. Verify plumb immediately after fastening each stud. Adjust before proceeding to the next.
Fixed Base Clip Angle Connection CONCRETE SLAB / STEEL BEAM Horizontal leg (fastened to structure) Vertical leg (screwed to stud web) CFS stud (152 or 203mm) HWH screws Concrete anchors 50mm min 50mm min FIXED CONNECTION No vertical movement Resists wind shear
Fig 1 — Fixed base clip angle connection: L-shaped clip fastened to structure with concrete anchors or TEK screws, and to stud web with HWH self-drilling screws. No vertical movement — this is the fixed support point.

Pro Tip: Pre-fabricate clip angles in bulk on the ground before starting installation. Set up a jig with a drill press or magnetic drill to punch consistent hole patterns in every clip. Field-drilled clips done one at a time on a ladder are slower, less accurate, and produce more scrap. A crew of two can fabricate a full floor’s worth of clips in a morning.

5. Connection to Structure — Top (Deflection)

At the top of each storey, the curtain wall studs connect to the beam or slab above with slotted clip angles or proprietary deflection clips. This is the critical detail that distinguishes curtain wall framing from load-bearing walls. The top connection must accomplish two seemingly contradictory things: resist wind loads (push and pull) while allowing the structure above to deflect vertically without crushing the stud.

Why Deflection Clips Are Essential

Structural steel beams and concrete slabs deflect under load. A steel beam spanning 12 m with L/360 allowable deflection will deflect up to 33 mm under full design load. A concrete slab continues to creep and deflect for years after construction. If the curtain wall stud is rigidly connected at the top, that deflection compresses the stud axially — a load the stud was never designed to carry. The result: buckled studs, cracked drywall, blown-out sheathing, and a very expensive rebuild.

Slotted Clip Angles

Proprietary Deflection Clips

Deflection Allowance Calculation

The deflection allowance at the top clip must account for the maximum expected deflection of the structure above. For a beam or slab spanning L:

Deflection (Slotted) Clip Angle Connection STEEL BEAM / CONCRETE SLAB ABOVE Vertical slot (20-25mm) Screw at MID-SLOT with washer Fixed to beam CFS stud Beam deflects downward Stud slides in slot DEFLECTION CONNECTION Resists wind (push & pull) Allows vertical movement Screw snugged, NOT torqued
Fig 2 — Deflection (slotted) clip angle at top of stud: vertical slots in the stud-side leg allow the stud to slide vertically as the beam above deflects. Screw installed at mid-slot with washer, snugged but not fully torqued.

Critical: Screw Position in Slot: The screw in the deflection clip must be installed at the mid-point of the slot, not at the top or bottom. If the screw is at the top of the slot, there is no room for the stud to move upward (thermal expansion, construction tolerances). If the screw is at the bottom, there is no room for downward deflection of the beam. Mid-slot gives equal travel in both directions. Mark the mid-point on every clip before fastening.

The number of times I’ve found deflection clips with the bolt jammed at the bottom of the slot could fill a book. A very expensive book about walls that cracked.

— A building envelope reviewer who checks every clip with a flashlight and a mirror

6. Complete Wall Assembly (Outside to Inside)

A curtain wall is not just studs — it is a multi-layered assembly where every component has a specific function in controlling heat, air, moisture, and vapour. Understanding the purpose of each layer and its position in the assembly is essential for correct installation. Getting the order wrong, or omitting a layer, creates problems that are invisible during construction but devastating in service.

Assembly Layers

  1. Cladding: The outermost visible layer — brick veneer, metal panel, ACM (aluminum composite material), fibre cement, stone veneer, or EIFS. Protects everything behind it from direct rain and UV exposure.
  2. Drainage cavity / air space: Minimum 25 mm clear space behind masonry veneer (19 mm minimum behind panel cladding) for drainage of any moisture that penetrates the cladding.
  3. Air barrier / weather-resistive barrier (WRB): Self-adhered membrane or fluid-applied coating on the exterior face of the sheathing. Prevents air infiltration and acts as the secondary rain screen.
  4. Continuous insulation (CI): Rigid insulation board installed continuously over the entire exterior of the sheathing, with no gaps at studs. This is the primary thermal control layer.
  5. Exterior sheathing: DensGlass (glass mat gypsum sheathing) or exterior-grade gypsum board. Provides a substrate for the air barrier and lateral bracing for the studs.
  6. CFS studs with cavity insulation: Batt insulation (mineral wool or fibreglass) between studs. Provides additional R-value and sound attenuation.
  7. Vapour barrier: 6-mil polyethylene or equivalent vapour retarder. In Ontario (Climate Zone 6), the vapour barrier is located on the warm side (interior side) of the insulation. Its position depends on climate — always outboard of the dew point to prevent condensation.
  8. Interior finish: Gypsum drywall (12.7 mm or 15.9 mm Type X for fire-rated assemblies).
Curtain Wall Assembly — Cross Section (Plan View) EXTERIOR INTERIOR 1. Cladding (brick veneer) 2. Air/drain cavity 25mm 3. Air/WRB 4. Continuous insulation (CI) 5. Sheathing 6. CFS studs + cavity insulation 7. VB 8. Drywall 1 2 4 6 8 Wind Heat loss CI layer breaks thermal bridge at steel studs
Fig 3 — Curtain wall assembly layers in plan view (outside to inside): brick cladding, drainage cavity, air/weather barrier, continuous insulation, exterior sheathing, CFS studs with cavity insulation, vapour barrier, drywall. The CI layer (4) is the critical thermal break that prevents steel stud thermal bridging.

Eight layers. Each one depends on the one before it. Skip one and the wall fails. Get the order wrong and the wall fails. Build them all correctly and the building lasts fifty years without a complaint. That’s the deal.

— A building science professor who makes every student memorize the wall assembly in their sleep

7. Continuous Insulation (CI) — Detailed

Continuous insulation is the single most important thermal element in an exterior steel stud wall. Without CI, the wall’s thermal performance is a fraction of what the cavity insulation alone would suggest, because steel studs are massive thermal bridges. Steel conducts heat roughly 300 times more efficiently than wood. A 152 mm steel stud wall with R-22 batt insulation but no CI performs like approximately R-8 to R-9 in practice — a 40–60% reduction in effective R-value from the steel studs alone.

Continuous insulation solves this by wrapping the entire exterior of the wall in an unbroken thermal blanket. Because the CI is outboard of the studs, it insulates the studs themselves, reducing the thermal bridging effect to near zero.

CI Material Comparison

MaterialR-value per 25mmKey AdvantagesKey Concerns
XPS (extruded polystyrene)R-5High R/inch, moisture-resistant, dimensionally stableHigher GWP (global warming potential), some jurisdictions restricting use
EPS (expanded polystyrene)R-4Economical, lower GWP than XPS, widely availableLower moisture resistance, slightly lower R/inch
Mineral wool (Roxul ComfortBoard)R-4.2Non-combustible, excellent fire performance, vapour-permeable (allows drying)Heavier, more expensive, requires care in handling
Polyisocyanurate (polyiso)R-6Highest R/inch, foil-faced acts as vapour retarderR-value drops below −15°C — must be derated for Ontario winter exterior

Ontario Climate Zone 6 Requirements

CI Board Installation

Best Practice: CI products and thicknesses are specified by the building envelope consultant. Field substitutions are never acceptable — even swapping XPS for EPS of the same thickness changes the thermal performance, moisture behaviour, and potentially the fire rating of the assembly. If the specified product is unavailable, contact the project manager for a formal substitution request through the consultant.

Pro Tip: When installing mineral wool CI boards, handle them with care — they are denser and heavier than foam boards and can crack or delaminate if flexed aggressively. Stage the boards flat on clean pallets, protected from rain. Wet mineral wool retains water for a long time and loses R-value until it dries. Plan your installation sequence so boards go on the wall the same day they come off the pallet.

8. Cladding Support Through CI

The cladding must be attached to the structural framing, but it sits outboard of the continuous insulation. Every fastener or bracket that penetrates the CI creates a point thermal bridge — a direct conductive path through the insulation layer. The goal of modern curtain wall design is to support the cladding while minimizing these thermal bridges.

Thermal Spacer Systems

SystemDescriptionBest For
Armatherm Z-GirtStructural thermal break pads made from fibre-reinforced polymer. Installed between the steel Z-girt and the stud to break the thermal bridge.Metal panel, fibre cement, general cladding support
Knight Wall SystemsEngineered bracket system with thermally broken clips. The bracket extends through the CI and connects to the stud while maintaining a thermal break.Heavier cladding, stone veneer, thick CI assemblies
Cascadia ClipFibreglass-reinforced clip that attaches to the stud through the CI. Accepts Z-girts or hat channels for cladding attachment.Standard metal panel, fibre cement, lighter cladding

Cladding-Specific Support

Thermal Bridge Warning: Every steel bracket, Z-girt, or angle that penetrates the CI without a thermal break reduces the effective R-value of the CI at that location by 80–100%. If 10% of the wall area has unbroken thermal bridges, the overall CI performance drops by 15–25%. Thermal spacers are not optional — they are a code-required component of the energy performance of the assembly.

9. Air & Vapour Barriers

The air barrier and vapour barrier are two distinct control layers in the wall assembly, each with a specific job. They are often confused, sometimes combined into a single product, and frequently installed incorrectly. Getting these layers right is essential for a building envelope that performs over its lifespan without moisture damage, mould, or energy waste.

Air Barrier

The air barrier prevents uncontrolled air leakage through the wall assembly. Air leakage carries moisture, heat, and pollutants. In a pressurized building (which churches often are, due to HVAC systems), warm moist interior air pushed through gaps in the envelope can deposit large quantities of moisture in the wall cavity — far more moisture than vapour diffusion alone. The air barrier is the single most important layer for controlling moisture in the assembly.

Air Barrier Continuity at Transitions

Vapour Barrier

The vapour barrier controls vapour diffusion — the slow movement of water vapour through materials from the warm, humid side to the cold, dry side. In Ontario (Climate Zone 6), the vapour barrier is installed on the interior (warm) side of the insulation to prevent warm, moist indoor air from diffusing into the cold wall cavity where it would condense.

Testing

Air barrier performance is verified through testing per OBC and NECB requirements. Common test methods include:

Pro Tip: Schedule air barrier inspection before the CI goes on. Once the continuous insulation covers the air barrier membrane, you cannot see it, inspect it, or fix it without removing the CI. A dedicated walkthrough of the completed air barrier — before any CI installation begins — catches every missed seal, torn membrane, and unsealed penetration while the fix is still simple and inexpensive.

10. Window & Door Integration

Windows and doors are the most vulnerable points in any curtain wall assembly. Every opening creates an interruption in the air barrier, vapour barrier, insulation, and cladding — four control layers that all need to be transitioned around the opening without gaps, laps in the wrong direction, or sealant joints that will fail in five years. Water damage at windows is the number one source of building envelope failures, and the fix is always expensive because it involves removing cladding, CI, and sometimes framing to access the damage.

Head, Sill, and Jamb Flashing

Sealant Joints

Subsill Membrane

The subsill membrane is a self-adhered or fluid-applied waterproof membrane applied to the rough sill of the window opening before the window is installed. It wraps up the sides of the opening a minimum of 150 mm and slopes outward to drain. This membrane catches any water that bypasses the window frame sealant and directs it to the exterior drainage plane. It is the single most important detail for preventing water damage at windows.

Large Church Window Openings

Church buildings frequently feature large window openings — full-height sanctuary glass, clerestory windows, feature windows in lobbies and towers. These large openings create significant structural and envelope challenges:

Water Damage at Windows: More building envelope failures start at windows than at any other location. The most common failure mode is water penetration at the sill — either from a missing subsill membrane, a membrane that was lapped incorrectly (directing water inward instead of outward), or sealant failure at the window-to-wall joint. Inspect every window rough opening for correct membrane installation before the window is set. After the window is in, the subsill is invisible and unfixable without removing the window.

11. Lateral Bracing of Curtain Wall Studs

Curtain wall studs, like interior partition studs, require lateral bracing to prevent twisting and buckling. The bracing requirements are often more demanding because curtain wall studs are taller, heavier gauge, and subjected to wind loads that create significant lateral forces.

Bracing Methods

Bracing at Corners and Returns

Where curtain walls meet at corners or return into the building, the framing requires additional bracing to handle the change in direction. Corner studs receive bridging from both wall planes, and the connection between the two planes must be rigid enough to transfer wind loads around the corner without racking. The engineer details these connections on the shop drawings — they are not field-improvised.

Pro Tip: Install all bridging and bracing before the exterior sheathing goes on. Once the sheathing covers the studs, threading CRC through the punches is impossible and strap bracing is inaccessible. Bridging is structural — it is not a punchlist item. If the inspection reveals missing bridging after sheathing, someone is removing sheathing.

12. Brick Veneer on Curtain Wall

Brick veneer is the most common cladding on Ontario church buildings, and it creates the most complex curtain wall assembly. The brick is heavy (approximately 2.0 kN/m² for standard 90 mm veneer), it requires structural support at every floor line, it needs a drainage cavity behind it, and every piece of metal that connects the brick to the structure passes through the continuous insulation — creating thermal bridges that must be managed.

Shelf Angle Support

Brick Ties

Expansion Joints

Drainage Cavity

Flashing

Brick Veneer on Curtain Wall — Section at Shelf Angle SLAB EDGE Shelf angle Thermal break Soft joint 25mm cavity CI Stud Brick tie Flashing Weep Water drains down Key Requirements: - 25mm min drainage cavity - Shelf angle at each floor - Thermal break at shelf angle - Soft joint below shelf angle - Weeps at 600mm o.c. - Flashing at every support
Fig 4 — Brick veneer on curtain wall at shelf angle: brick supported on shelf angle bolted to slab edge (with thermal break), soft joint below angle for expansion, drainage cavity behind brick, flashing at shelf angle directing water to weep holes.

Brick looks like it lasts forever. And it does — as long as every piece of flashing, every weep hole, and every soft joint behind it is doing its invisible job. The brick is just the face. The face is the easy part.

— A mason who has torn out more walls than most people have ever built

13. Metal Panel & ACM Cladding

Metal panel and ACM (Aluminum Composite Material) cladding provide a modern, clean aesthetic that many contemporary church designs use for fellowship halls, office wings, gymnasiums, and accent walls. The cladding is lighter than brick, faster to install, and offers more flexibility in colour and profile. The underlying curtain wall framing and envelope assembly remain the same — the difference is in the cladding support system.

Sub-Framing

Panel Clip Systems

Joint Details

ACM Fire Concerns

ACM and Fire Safety (Post-Grenfell): Following the Grenfell Tower fire (London, 2017), Ontario and Canadian building codes have increased scrutiny on ACM panels. ACM panels with polyethylene (PE) cores are combustible and may not be permitted on buildings over certain heights or in certain occupancy classifications. Only fire-rated ACM panels with mineral-filled (FR) cores should be used on church projects (Group A, Division 2 occupancy). Verify the specific ACM product’s fire test reports and confirm compliance with OBC Part 3 combustibility requirements before specifying or installing.

14. Quality Control & Inspection

Curtain wall framing and envelope construction involve dozens of components, hundreds of connections, and thousands of potential failure points. Quality control is not a single inspection at the end — it is a continuous process integrated into every phase of the work. The cost of fixing envelope deficiencies after the wall is complete is 10–50 times the cost of getting it right during installation.

Pre-Installation Checks

During Installation

Envelope Inspection

Post-Installation

Inspect it when you can see it. Once it’s buried under three layers of insulation and brick, the only way to inspect it is with a demolition crew.

— A quality control inspector who carries a camera with 4,000 photos of hidden deficiencies

15. Common Mistakes

These are the errors that show up repeatedly on curtain wall and envelope projects. Every one of them has caused expensive repairs, insurance claims, or occupant complaints. Learning them here is considerably cheaper than learning them on the job.

  1. Missing or inadequate deflection clips. Studs rigidly connected to the structure at the top get crushed when the beam deflects. The entire wall buckles, the cladding cracks, and the only fix is a complete rebuild. This is the most expensive single error in curtain wall framing.
  2. CI board gaps at joints. Every gap — even 3 mm — is a thermal bypass and a potential condensation point. Cold spots behind gaps cause moisture accumulation, mould growth, and staining on interior finishes. Cut CI boards to fit tight and seal every joint.
  3. Air barrier discontinuity at transitions. The air barrier stops at the parapet. The air barrier stops at the window rough opening. The air barrier has unsealed laps. Every discontinuity allows air leakage, which carries moisture into the wall cavity. The result: condensation, rot, mould, and energy waste.
  4. Brick ties too widely spaced or wrong type. Under-tied brick veneer is a structural hazard — the veneer can separate from the wall under wind suction. Using non-adjustable ties on a curtain wall forces the mason to bend the ties to fit, reducing their capacity and durability.
  5. Insufficient drainage cavity behind brick. Mortar droppings filling the drainage cavity blocks water flow to the weep holes. Water backs up behind the brick and eventually finds a path into the wall assembly. Clean cavities during construction — every day the mason works.
  6. Flashing reversed (directs water inward). Through-wall flashing that slopes inward instead of outward collects water and delivers it to the wall cavity instead of the exterior. Every flashing must slope to drain to the outside. Check the slope on every piece before the next course of brick covers it.
  7. Vapour barrier on wrong side of assembly. In Ontario, the vapour barrier goes on the warm side (interior). A vapour barrier on the cold side (exterior) traps moisture inside the wall cavity — the wall cannot dry inward, and condensation accumulates through every heating season. This error is invisible until the wall is opened for other reasons, by which time the damage can be extensive.
  8. Cladding attached directly to studs without thermal break. Mounting Z-girts or shelf angles directly to the studs through the CI without thermal spacers creates massive thermal bridges that negate the benefit of the CI. The CI exists to break the thermal bridge — do not re-create the bridge at every cladding attachment point.

Every one of these mistakes has a name attached to it somewhere. Most of them also have a repair invoice. The repair invoice is always bigger than the prevention cost. Always.

— A project manager who keeps a “lessons learned” binder thicker than most novels

16. Commercial Interior Glazing

Interior glazing on church projects goes far beyond a pane of glass in a frame. Nursery observation windows, office partitions, meeting-room dividers, sidelites, transoms, and mirrors all require the right glass type, the right framing system, and strict compliance with OBC safety-glazing rules. In Ontario, all commercial glazing work must be performed by or under the direct supervision of a certified Glazier & Metal Mechanic (421A) journeyperson — this is a compulsory trade under Skilled Trades Ontario regulations.

Glass Types for Interior Applications

Glass TypeDescriptionTypical Church Application
TemperedHeat-treated to 4–5× the strength of annealed glass. Breaks into small, relatively harmless cubes rather than sharp shards.Interior partitions, sidelites, borrowed lites, glass doors, any safety-glazing location
LaminatedTwo glass layers bonded with a PVB (polyvinyl butyral) interlayer. Holds together when broken — the interlayer keeps fragments in place.Nursery observation walls, balcony guards, overhead glazing, security applications
Fire-Rated WiredGlass with embedded wire mesh that holds the pane together during fire exposure. Legacy technology being phased out.Older fire-separation glazing. No longer permitted in hazardous (impact-risk) locations per updated OBC provisions.
Fire-Rated CeramicSpecially manufactured ceramic glass that maintains integrity and, in some products, insulation during fire exposure. Ratings from 20 to 120 minutes.Fire-separation glazing, corridor sidelites, rated door vision panels. The modern replacement for wired glass.

Interior Storefront & Office Partition Framing

Interior storefront framing uses aluminium frames — typically non-thermally-broken for interior applications since there is no temperature differential across the assembly. Standard frame depths are 44 mm or 50 mm face width, with finishes in clear anodized, dark bronze anodized, or powder-coated to match door hardware.

OBC Safety-Glazing Requirements

OBC 3.3.1.2 mandates safety glazing (tempered or laminated) in specific locations. Inspectors check these on every project — memorize them:

Church Applications

The building committee wanted the nursery “completely sealed off for safety” but also “completely open so parents can see.” Laminated glass solved both problems. The kids are contained, the parents can watch, and the three-year-old who threw a sippy cup at the window only left a smudge instead of a disaster.

— A glazier who has installed more nursery observation walls than he can count

Pro Tip: When laying out interior glazing near doors, measure the 500 mm safety-glazing zone from the door edge including the frame, not just the door leaf. Inspectors measure from the nearest door edge, which includes the frame stop. Getting this wrong means replacing annealed glass with tempered after the inspection — an expensive and embarrassing rework.

17. Exterior Storefront & Entrance Systems

The church entrance is the handshake — the first physical interaction every visitor has with the building. A well-designed, properly installed storefront entrance system says “welcome.” A drafty, rattling, leaking entrance says “we ran out of budget.” Exterior storefront glazing must perform structurally (wind loads), thermally (Ontario winters), and aesthetically — simultaneously.

Aluminium Storefront Systems

System TypeDescriptionPerformance
Captured (Pressure-Plate)Glass held in place by an exterior pressure plate screwed to the frame. Pressure plate is covered by a snap-on cover cap. Most common system for church projects.Proven, maintainable, glass replaceable from outside. Thermal break versions meet OBC energy requirements.
Flush-Glaze (Structural Silicone)Glass bonded to the frame with structural silicone sealant on two or four sides. Exterior surface is flush — no visible pressure plate.Sleek modern appearance. Higher cost. Four-side SSG requires engineering certification.
Toggle-Glaze (Inside-Set)Glass installed from inside the building. Exterior snap covers may or may not be present.Useful where exterior access is limited (upper-storey glazing). Avoids scaffolding for glass replacement.

All exterior storefront on church projects in Ontario must use thermally broken frames — frames with a polyamide (nylon) bridge separating the interior and exterior aluminium to prevent thermal bridging. Non-thermally-broken frames cause condensation, energy loss, and will not meet OBC Part 5 (SB-10) energy-code requirements. Specify low-E, argon-filled insulating glass units (IGUs) as minimum.

Entrance Door Frames

Automatic Entrance Systems

OBC barrier-free requirements and AODA mandate power-operated doors at barrier-free entrances. Options for church projects:

Integration with Curtain Wall Systems

Storefront entrance systems frequently butt against or integrate into the curtain wall framing covered earlier in this guide. Key coordination points:

Church Vestibule Entrance Design

Thermal Performance Considerations

The building committee wanted a wall of glass facing the sunrise for Easter services. Beautiful vision. Then I explained what east-facing full-height glass does to a sanctuary at 7 a.m. in July. We added solar shades and specified low-SHGC glass. The Easter sunrise is still glorious. The July Bible study no longer feels like a greenhouse.

— A glazier who carries a solar heat-gain chart and a compass in his toolbox

Pro Tip: Before ordering storefront shop drawings, field-verify every structural steel anchor point for plumb and location. Storefront framing is manufactured to tight tolerances — if the steel is 15 mm out of plumb, the storefront will either rack to match (visible and unacceptable) or require shimming at every anchor (time-consuming and expensive). Catch the deviation before the shop drawings, not after the frames arrive on site.

Compulsory Trade — 421A Glazier & Metal Mechanic: Under Skilled Trades Ontario regulations, glazing is a compulsory-certification trade. Any person who installs, replaces, or repairs commercial glass, mirrors, storefront systems, or entrance assemblies must hold or be apprenticing toward a 421A certificate. Verify trade certification for all glazing subcontractors before they set foot on site.

18. Standards, Codes & Reference Documents

Every section of this guide ties back to specific codes, standards, and manufacturer requirements. Here is the master reference list for curtain wall framing and building envelope on church construction projects in Ontario.

Standard / CodeRelevance to Curtain Wall & Envelope
Ontario Building Code (OBC) Part 3Fire protection, occupant safety — churches are Group A, Division 2 assembly occupancy. Drives combustibility requirements for cladding and fire separation from property lines.
OBC Part 4Structural design — all curtain wall framing, clip connections, and bracing are engineered under Part 4.
OBC Part 5Environmental separation — air barriers, vapour barriers, rain penetration control, thermal insulation. The code requirements for the building envelope.
CSA S136North American Specification for the Design of Cold-Formed Steel Structural Members — member and connection design for CFS curtain wall studs.
AISI S240North American Standard for Cold-Formed Steel Structural Framing — wall stud framing systems, headers, bracing.
NECB (National Energy Code for Buildings)Energy performance requirements for building envelopes — CI thickness, effective R-values, air barrier performance, thermal bridging limits.
CSA A371 (Masonry Construction for Buildings)Requirements for brick veneer construction — tie spacing, mortar joints, expansion joints, shelf angle support.
CCMC EvaluationsCanadian Construction Materials Centre evaluations for CI products, thermal spacer systems, air barrier products, and cladding attachment systems. Provides code compliance confirmation for proprietary products.
ASTM A1003Standard specification for steel sheet for cold-formed framing members — defines Grade 33 (228 MPa) and Grade 50 (345 MPa).
ASTM E1105Standard test method for field determination of water penetration of installed exterior windows, skylights, doors, and curtain walls — used for mock-up testing.

Related Article: For interior steel stud framing, light-gauge partitions, fire-rated assemblies, sound-rated assemblies, deflection head tracks, and general fastener information, see the Steel Stud & Heavy Gauge Steel Framing article.

The building envelope is a system. Every layer depends on every other layer. The framing holds it up, the barriers keep it dry, the insulation keeps it warm, and the cladding keeps it looking good. Miss one layer, and the system fails. Build them all right, and the building takes care of the people inside it for a lifetime.

— The building science instructor who draws wall sections in their sleep and is completely fine with that

Recommended Videos

Back to Employee Portal