Quick Reference — Hoisting & Rigging at a Glance

Sling Angle Tension Factors

Sling AngleTension FactorStatus
90° (vertical)1.00×Ideal
60°1.16×Acceptable
45°1.41×HCMI minimum
30°2.00×Prohibited

Sling Hitch Capacity Factors

Hitch TypeCapacity Factor
Vertical (straight pull)1.0 (100%)
Choker0.75 (75%)
Basket (single wrap, 90°)2.0 (200%)

Material Densities

MaterialDensity (kg/m³)
Structural steel7 850
Concrete2 400
Glulam timber500–600
Aluminium2 700
Water1 000

Critical vs. Non-Critical Lift

  • Non-critical: Load < 75% rated capacity, standard rigging, no overhead obstructions, no personnel under load
  • Critical (≥1 condition): ≥ 75% capacity, tandem pick, over occupied area, steeple/tower element, or marginal conditions
  • Critical lift = P.Eng. stamp required — no exceptions

Key Hand Signals (CSA Z150)

  • Hoist: Index finger up, rotate in circles
  • Lower: Index finger down, rotate in circles
  • Stop: Arm extended, palm down, sweep horizontal
  • Emergency Stop: Both arms, palms down, sweep rapidly
  • Dog Everything: Clasp hands at waist

Safety Rules

  • One signaller at a time — anyone can give E-stop
  • Chain: Only Grade 80/100 alloy for overhead lifting. Never Grade 30/43.
  • Synthetic slings: Never near flame/welding; destroy if exposed to heat
  • >75% capacity: Verify weight with load cell before lift
  • Spreader bars: Must be P.Eng.-designed (O. Reg. 213/91 s. 153)
  • Wind: Operator has absolute authority to stand down
📄 Download printable cheat sheet

Every church project has a moment that defines the project: the first steel truss swinging over the sanctuary walls, a 4 500 kg rooftop unit settling onto the fellowship-hall curb, or a steeple section rising 30 metres into a clear Ontario sky. Those moments only happen because somebody rigged the load right, a qualified operator ran the crane, and a signaller kept the whole ballet moving on one frequency. Hoisting and rigging is where physics meets craftsmanship, and there is zero room for “close enough.”

This guide covers every skill in Category 10 — from hand signals and radio protocol through sling selection, lift planning, mobile equipment, and rigging inspection. The standards are Canadian: CSA Z150 for crane safety, O. Reg. 213/91 for construction projects, and the Ontario College of Trades licensing that makes crane operation a compulsory trade in this province. If it doesn’t carry a Canadian standard number, it doesn’t belong on a church construction site.

Whether you’re a first-year apprentice learning to tie a tag line or a seasoned rigging foreperson planning a critical lift, the information here is what keeps loads in the air and workers on the ground — alive and uninjured.

Gravity never takes a day off. Neither does your rigging plan.

— A crane operator who doesn’t find crane jokes funny anymore

Ontario Licensing Note: Mobile crane operation is a compulsory trade in Ontario. You must hold a valid Certificate of Qualification — 339A (Mobile Crane Operator — Hydraulic) or 339B (Mobile Crane Operator — Lattice Boom, Friction) — or be a registered apprentice working under direct supervision. Tower crane operation requires 339C or 839A. Operating without certification is an offence under the Ontario College of Trades and Apprenticeship Act.

1. Crane Signalling: Hand Signals & Radio Communication (10.01–10.02)

A crane is only as safe as the communication between the operator and the signaller. CSA Z150 requires that a designated signaller be assigned for every hoisting operation where the operator cannot see the load, the landing area, or the swing path. On church construction sites — where steel columns disappear behind masonry walls and rooftop units land on roofs the operator can’t see — that means a signaller is needed on almost every lift.

10.01 — Hand Signals per CSA Z150

Hand signals are the universal fallback. Radios die, batteries go flat, channels get crossed — but hand signals always work. CSA Z150 Annex B defines the standard set. Every person on site who may act as a signaller must demonstrate competency in these signals before the first crane day.

SignalArm / Hand PositionWhen Used
Hoist (raise)Index finger up, rotate hand in small circlesLifting the load or hook
LowerIndex finger down, rotate hand in small circlesLowering the load or hook
Boom UpArm extended, thumb up, fingers closedRaising the boom angle
Boom DownArm extended, thumb down, fingers closedLowering the boom angle
Swing Left / RightArm extended, point in direction of swingRotating the crane superstructure
Travel (crawler / truck)Both fists in front, rotate around each other; direction indicated by raised thumbMoving the entire crane
StopArm extended, palm down, sweep horizontallyStop current motion
Emergency StopBoth arms extended, palms down, sweep rapidlyImmediately cease all crane motion
Dog EverythingClasp hands together at waist levelSuspend operations, hold position

Critical Rule: Only one designated signaller communicates with the operator at any time. Anyone — anyone — may give an emergency stop, but only the designated signaller gives operational commands. Two people waving directions is how loads end up through a wall.

10.02 — Radio Communication Protocol

On most HCMI lifts, dedicated two-way radios should be used on a channel reserved exclusively for hoisting operations. No chatter about lunch orders, no superintendent calling about the drywall delivery. Crane channel is crane channel.

Pro Tip — The Two-Signal System: A common practice is a belt-and-suspenders approach. The primary signaller uses radio for routine commands, but switches to hand signals whenever the load is within 3 metres of its final position. The slow, precise movements needed for final placement are easier to control visually. Radio for the journey, hands for the landing.

2. Rigging Slings & Hardware (10.03–10.07)

The sling is the link between the crane hook and the load. Choose the wrong sling, use a damaged sling, or rig at the wrong angle, and you’re not just dropping a load — you’re launching a projectile. Every sling type has its strengths, its limits, and its failure mode. Know all three.

10.03 — Wire Rope Slings

Wire rope slings are the workhorse of structural steel rigging. They handle abrasion, heat near welding operations, and the sharp edges of steel beams better than any synthetic. On HCMI steel-erection days, wire rope is the default choice.

10.04 — Synthetic Slings (Nylon & Polyester)

Synthetic web slings and round slings are gentler on finished surfaces — ideal for setting pre-finished architectural panels, glass curtain-wall units, or that custom millwork cross for the sanctuary feature wall. They’re lighter to handle and conform around irregular shapes.

Synthetic Sling & Heat: Nylon and polyester slings must never be used near open flame, torch cutting, or welding splatter. Nylon melts at approximately 220 °C; polyester at 260 °C. A single spark can weaken the fibre without visible damage. If a synthetic sling has been exposed to heat, destroy it — cut it in half and throw it in the bin. Do not leave it where someone might re-use it.

Sling Hitch Types & Capacity Factors

The way you attach the sling to the load — the hitch type — changes the sling’s effective capacity. A vertical hitch uses 100% of the rated capacity. A choker hitch reduces it. A basket hitch can increase it (if the load stays balanced). Every rigger must know these factors by heart.

Hitch TypeCapacity FactorBest ForWatch Out For
Vertical (straight pull)1.0 (100%)Loads with engineered lift points (pad eyes, lift lugs)Load must be balanced directly below the hook
Choker0.75 (75%)Loose bundles, round objects, pipes, logsSling can slip on smooth surfaces; crush damage on soft materials
Basket (single wrap)2.0 (200%) at 90°Wide, stable loads — steel beams, concrete panelsLoad must be balanced; slings can slide together on tapered loads
Double-wrap choker0.75 (per leg, with friction benefit)Loads that must not slip — round pipe, bundled rebarExtra time to rig and un-rig; can damage synthetic slings on sharp edges

10.05 — Chain Slings

Grade 80 or Grade 100 alloy chain slings are virtually indestructible by abrasion and can handle high-temperature environments. They’re the heaviest option, so they add significant tare weight — important when you’re close to the crane’s rated capacity. HCMI keeps chain slings on site primarily for steel erection where wire rope might be damaged by sharp flame-cut edges.

10.06 — Rigging Hardware: Shackles, Hooks, Swivels, Turnbuckles

Hardware is the connector between the sling and the load — or between the sling and the crane hook. Every piece of hardware has a Working Load Limit (WLL) stamped on it. No exceptions, no guessing, no “it looks big enough.”

Pro Tip — The Shackle Pin Rule: Screw the pin finger-tight, then back it off a quarter turn. On a long lift day with temperature changes, a pin torqued tight can seize. A pin that’s been backed off a quarter turn comes apart at the end of the day without a cheater bar. And always mouse the pin with wire on critical lifts — vibration can rotate an un-moused pin right out of the shackle.

10.07 — Spreader Bars & Lifting Beams

When the load is long, flexible, or needs to stay level during the lift, you use a spreader bar or a lifting beam. Church projects use these constantly — long-span sanctuary trusses, pre-cast wall panels, glulam beams, and curtain-wall assemblies all require multiple pick points kept apart by a rigid bar.

I’ve seen guys try to pick a 16-metre truss with two choker hitches 3 metres apart. The truss bowed like a banana and started rolling. We shut it down, brought in the spreader bar, and did it right. Took an extra 30 minutes. Doing it wrong would have taken an extra 30 days — of paperwork, repairs, and Ministry visits.

— A rigging foreperson who considers a spreader bar cheap insurance and a shortcut expensive therapy

3. Sling Angles & Load Calculation (10.14)

The angle between the sling and the horizontal — the sling angle — is the single most misunderstood factor in rigging. As the angle decreases (slings spread wider), the tension in each sling increases dramatically. A 30-degree sling angle doubles the load on each sling leg compared to a vertical hitch. Go to 15 degrees and you’re in territory where slings fail and loads fall.

Sling Angle vs. Sling Tension Factor Crane Hook LOAD 90° = 1.00× (Vertical — ideal) LOAD 60° = 1.16× (Common — acceptable) 60° LOAD 30° = 2.00× (Dangerous — double tension!) HCMI Minimum Sling Angle: 45° Below 45° requires a P.Eng.-approved rigging plan. Below 30° is prohibited on all projects.
Figure 1 — As the sling angle decreases from vertical, tension in each sling leg increases. The multiplier equals 1 / sin(angle). At 30°, each sling carries twice the proportional load.

10.14 — Load Weight Estimation

Before you can select slings or plan a lift, you need to know what the load weighs. Guessing is not an option. On church construction projects, a common approach is to use three methods — in order of reliability:

  1. Manufacturer data: Steel shop drawings list piece weights. Mechanical equipment has a nameplate weight. Pre-cast panels have an engineer’s weight calculation. Use these first.
  2. Calculated weight: Volume × density. Steel = 7 850 kg/m³. Concrete = 2 400 kg/m³. Water (for ballast or tanks) = 1 000 kg/m³. A W310×67 beam that’s 12 m long weighs 67 kg/m × 12 m = 804 kg. Add rigging weight.
  3. Field estimation (last resort): For oddly shaped loads, calculate the volume of the bounding box, multiply by material density, and add 10–15% as a safety margin. Then weigh it with a load cell if it’s anywhere near the crane’s rated capacity.

HCMI Weight Estimation Rule: If the estimated load weight exceeds 75% of the crane’s rated capacity at the required radius, you must verify the weight with a calibrated load cell or certified scale before the lift proceeds. No exceptions. The crane’s load-moment indicator (LMI) is a backup, not a scale.

MaterialDensity (kg/m³)Common Church Application
Structural steel7 850Beams, columns, trusses, lintels
Normal-weight concrete2 400Pre-cast panels, tilt-up walls, stairs
Glulam timber500–600Exposed sanctuary beams, arches
Aluminium curtain wall2 700Entrance feature walls, clerestory glazing
Rooftop HVAC unitVaries (check nameplate)Packaged RTUs, make-up air units
Water (for testing / ballast)1 000Sprinkler tank commissioning, counterweights

4. Lift Planning: Critical & Non-Critical Lifts (10.08)

O. Reg. 213/91 and CSA Z150 both require a documented lift plan for any crane operation. The depth of that plan depends on whether the lift is classified as critical or non-critical.

Non-Critical Lift

A non-critical (routine) lift meets all of the following conditions:

Non-critical lifts still require a written lift procedure documented on the project lift-procedure form. The operator, signaller, and rigging crew review it together at the pre-lift meeting. This is not optional — even if you’ve made the same pick 50 times.

Critical Lift

A lift is classified as critical if any of the following conditions exist:

Critical Lift = P.Eng. Stamp Required: Under O. Reg. 213/91 and HCMI policy, every critical lift plan must be prepared or reviewed and stamped by a Professional Engineer licensed in Ontario. The plan must include: crane selection and configuration, load weight verification, rigging design with safety factors, ground-bearing analysis, environmental limits (wind speed, temperature), exclusion zones, and an emergency procedure. No P.Eng. stamp — no lift. Period.

We were setting the sanctuary roof trusses at a church in Kitchener — 22-metre clear span, 3 200 kg each, the crane was at 82% capacity at the farthest radius. That made it a critical lift. The engineering took two weeks and cost $4 000. One of the trusses shifted during landing and the crane’s LMI alarmed. Because we had a P.Eng. plan, we knew exactly what to do: set the load down, re-rig at a shorter radius, and try again. Without that plan, someone might have panicked and done something dangerous. Four thousand dollars is cheap insurance.

— A superintendent who plans crane days the way NASA plans launches

Pro Tip — The Pre-Lift Checklist: Before every lift, the operator, signaller, and rigging crew conduct a 5-minute toolbox talk covering: (1) load weight, (2) rigging configuration, (3) lift radius and crane capacity at that radius, (4) swing path and obstructions, (5) landing zone and tag-line plan, (6) wind conditions, (7) who is the designated signaller. If anyone cannot answer all seven items, the lift does not proceed until they can.

5. Mobile Equipment Operations (10.09–10.12)

Church construction sites use a range of mobile hoisting equipment, from small warehouse forklifts moving drywall bundles to 200-tonne mobile cranes setting structural steel. Each machine has its own licensing requirements, operating envelope, and ways to hurt people.

EquipmentSkillOntario CertificationCommon Church-Site Use
Forklift (warehouse / yard)10.09Employer-certified training (CSA B335)Material handling — drywall, lumber, steel decking, mechanical equipment in staging area
Telehandler10.10Employer-certified training (CSA B335 category)Elevated material placement — block, steel joists, roofing materials, glass panels to upper floors
Boom truck (truck-mounted crane)10.11339A (Hoisting Engineer — Mobile Crane Operator, Hydraulic) — compulsory tradeLight to medium picks — RTU setting, steel lintels, small trusses, precast sills
Tower crane10.12339C or 839A (Tower Crane Operator) — compulsory tradeLarge campus builds — multi-storey church/school complexes, urban sites with restricted crane access

10.09 — Forklift Operation

The humble forklift does more material handling on a church site than any other machine. It’s also the most commonly abused. CSA B335 requires operator training that includes both classroom theory and practical evaluation, documented by the employer.

Church-Site Forklift Hazard: Many church projects are on active campus properties. Congregation members, staff, and visitors may be walking through or near the staging area — especially on Sunday mornings if the existing building remains in use. Best practice is to install a physical barricade (jersey barriers or fencing) between the forklift operating zone and any pedestrian path. Cones and caution tape alone are not sufficient when the public is present.

10.10 — Telehandler Operation

Telehandlers combine reach with lifting capacity — they’re the Swiss Army knife of church construction. A typical 3 600 kg telehandler can place material at heights up to 12 metres, which covers most two-storey church builds. But the load chart is three-dimensional (capacity varies by boom extension and boom angle), and operators must understand it completely.

10.11 — Boom Truck Operation

Boom trucks (truck-mounted hydraulic cranes) are the most common crane type on church construction projects. They drive to the site, set up outriggers, make the picks, and drive away. Most RTU sets, steel lintel placements, and light truss picks are done with a boom truck in the 20–50 tonne class.

Church-Site Scenario: Setting Rooftop Units on a Fellowship Hall

One of the most common boom-truck lifts on church projects is setting packaged rooftop HVAC units on a fellowship hall or gymnasium roof. A typical RTU weighs 1 200–3 500 kg and must land precisely on a pre-installed curb adapter. The operator often cannot see the landing area from the cab.

10.12 — Tower Crane Operation

Tower cranes are rare on church projects but appear on large campus builds — multi-storey church/school complexes or urban infill sites where a mobile crane cannot access all areas. Operating a tower crane in Ontario requires a 339C or 839A Certificate of Qualification. There is no “I watched a YouTube video” shortcut.

We had a tower crane on the Brampton campus build — three-storey church with a gymnasium wing. The neighbours were nervous until we held an information session showing them the crane’s operating radius and our exclusion-zone plan. By the end of the project, they were bringing coffee to the operator. Community relations matter on church sites — the congregation has to live next door to these people forever.

— A PM who has learned that crane rental by the hour means every minute counts twice

Pro Tip — The 3-Second Rule for Wind: Before any crane lift, hold a flag or survey ribbon at the hook height for 3 seconds. If it’s streaming horizontally, you’re above 30 km/h and most crane operations should be suspended. An anemometer gives you exact numbers, but the visual check is a fast field verification. On HCMI sites, the crane operator has absolute authority to stand down for wind — no superintendent overrides the operator on weather.

6. Tag Lines, Load Control & Ground Crew Safety (10.13)

The crane picks the load. The rigger hooks it up. But the tag-line handler controls where the load goes once it leaves the ground. On a church site, where loads swing between partially erected walls and over crews working below, tag-line handling is one of the most important and most underappreciated jobs on the project.

10.13 — Tag Line Handling

Never Wrap a Tag Line Around Your Hand: If the load swings, shifts, or catches the wind, a wrapped tag line will pull you into — or under — the load. Hold the tag line with a relaxed grip. If the tension becomes uncontrollable, let go. The load can be recovered. You cannot.

I tell every new labourer the same thing on their first crane day: the tag line is not a leash. You don’t walk the load like a dog. You guide it like a suggestion. Light tension, steady hands, and if it starts going somewhere you don’t want it to go, you let go and get clear. The crane operator and the rigger will sort it out. Your job is to not become part of the incident report.

— A rigging foreperson whose new-worker orientation speech has been compared to a sermon — and is just as effective

Church-Site Scenario: Setting a Steeple Section

Steeple lifts are the signature moment of many church builds. A steeple section — typically a fibreglass or copper-clad assembly weighing 1 500–4 000 kg — is a tall, slender, high-centre-of-gravity load with enormous wind sail area. Every steeple lift should be classified as a critical lift, regardless of whether it exceeds the 75% capacity threshold.

Pro Tip — Pre-Fit on the Ground: Before hoisting a steeple section, trial-fit all connections on the ground. Bolt patterns, alignment pins, and utility conduits should all be verified at grade where adjustments take minutes, not hours. Every minute spent fitting at 30 metres is a minute the crane is at capacity and the crew is exposed to a suspended load overhead.

Fall-Zone Awareness

O. Reg. 213/91 s. 153(2) prohibits workers from being under a suspended load unless required by the operation and protected by a written procedure. On HCMI sites, the fall zone is barricaded with cones, caution tape, and signage. The signaller is responsible for verifying the zone is clear before giving the “hoist” signal.

7. Rigging Inspection & Maintenance (10.15)

A sling is only as good as its last inspection. Rigging equipment should be inspected at three levels:

  1. Pre-use (every shift): The rigger visually inspects every sling, shackle, hook, and piece of hardware before it goes on a load. Takes 60 seconds per piece. Catches the obvious — cuts, kinks, missing safety latches, bent hooks, illegible tags.
  2. Periodic (monthly): A qualified person (the rigging foreperson or designated competent worker) conducts a thorough inspection of all rigging on site, documented on the monthly rigging inspection form. Includes measurements of wire-rope diameter, chain-link elongation, and synthetic-sling stitching condition.
  3. Annual (before spring startup): All rigging is returned to the shop, cleaned, inspected to CSA and manufacturer standards, and tagged with a colour-coded annual inspection tag. Equipment that fails inspection is destroyed — not “set aside for light duty.” There is no “light duty” in overhead lifting.
Sling TypeReject If…Inspection Method
Wire rope10+ broken wires in one rope lay; 5+ in one strand; kinks; bird-caging; core protrusion; >5% diameter reduction; damaged fittingsVisual + calliper measurement
Synthetic webCuts, tears, or snags; melting or charring; acid/alkali damage; illegible or missing tag; knots; crushed or distorted fittingsVisual + tactile (feel for stiffness or grit in fibres)
Synthetic roundCover damage exposing core yarns; broken or pulled stitching; distorted fittings; heat damage; missing tagVisual + tactile
Chain (Gr. 80/100)>5% elongation of any link; gouges >10% of link diameter; bent, twisted, or cracked links; worn bearing surfaces; missing ID tagVisual + go/no-go gauge or calliper
ShacklesBent or distorted body; worn pin or pin hole (>10% of original); missing cotter pin or nut; cracks; illegible WLL markingVisual + pin fit check
HooksThroat opening >15% of original; twist >10°; cracks; damaged safety latch; worn saddleVisual + measurement

Pro Tip — The Colour-Tag System: A common approach is to use coloured zip-ties on all rigging to indicate annual inspection status. The colour changes each year (2025 = green; 2026 = blue; 2027 = yellow). If you pull a sling out of the rigging bin and it doesn’t have the current year’s colour, it goes back in the bin and gets inspected before use. No tag, no lift.

Storage & Care

Rigging Accountability: Every piece of rigging on site should be inventoried and assigned to a specific project. When the project is complete, rigging is returned to the shop, re-inspected, and logged back into inventory. This prevents “mystery slings” with no inspection history from ending up on the next job. If it’s not in the system, it doesn’t go on a hook.

Ontario Crane Licence Classes — Quick Reference

Ontario classifies hoisting engineers (crane operators) by equipment type and capacity. The following table summarises the compulsory-trade certificates relevant to church construction projects. All are administered through the Ontario College of Trades (now Skilled Trades Ontario).

CertificateDesignationEquipment CoveredApprenticeship Duration
339AHoisting Engineer — Mobile Crane Operator (Hydraulic)Hydraulic truck cranes, boom trucks, all-terrain cranes, rough-terrain cranes with hydraulic boom6 000 hours + 3 in-school sessions
339BHoisting Engineer — Mobile Crane Operator (Lattice Boom, Friction)Lattice-boom crawler cranes, truck cranes with lattice boom, friction-type machines6 000 hours + 3 in-school sessions
339CTower Crane OperatorSelf-erecting, top-slewing, luffing-jib, and hammerhead tower cranes4 000 hours + 2 in-school sessions
839ATower Crane Operator (conditional)Same as 339C — alternate entry path for experienced operatorsVaries — assessment-based
420AIronworker (Structural / Ornamental)Includes rigging within the journeyperson scope — sling selection, signalling, load attachment6 000 hours + 3 in-school sessions

Compulsory Trade Enforcement: Mobile crane operation and tower crane operation are compulsory trades in Ontario. Performing the work without a valid Certificate of Qualification (or registered apprenticeship under direct supervision) is an offence. Fines apply to both the individual and the employer. HCMI verifies every crane operator’s certification before they step into the cab on any project — a copy of the C of Q is kept in the project file.

Applicable Standards & References

Standard / RegulationRelevance to Hoisting & Rigging
CSA Z150Safety Code on Mobile and Tower Cranes — design, operation, maintenance, signalling, rigging
O. Reg. 213/91Construction Projects (Ontario) — hoisting requirements, crane setup, rigging, signalling, approach distances to power lines
CSA B335Safety Standard for Lift Trucks (forklifts, telehandlers) — operator training and competency requirements
CSA B167Overhead cranes, gantry cranes, monorails, hoists, and trolleys
ASME B30.9Slings — design, fabrication, testing, inspection (referenced by Canadian sling manufacturers)
Ontario College of TradesCompulsory certification for Mobile Crane Operator (339A/339B) and Tower Crane Operator (339C/839A)
Ironworker 420A scopeRigging is within the journeyperson ironworker scope of practice in Ontario
Professional Engineers OntarioP.Eng. stamp required for critical lift plans, custom lifting devices, and spreader bar/lifting beam design

Build it like you’re going to worship in it. Rig it like your family is standing underneath. Because on a church site, somebody’s family is always nearby.

— The unofficial motto of every crane crew that ever picked steel in the wind

Recommended Videos

  • Steel Erection Safety Training
    YouTube · Safety Training
    Rigging and steel erection safety fundamentals — covers sling selection, load calculations, and safe lifting practices for structural steel.
  • Structural Iron and Steel Workers
    YouTube · Trade Overview
    Overview of the ironworker trade including rigging, crane signalling, and structural steel erection procedures on commercial projects.
Back to Employee Portal